At a glance
- Data Center Dynamics reported the filing Nov. 20.
- A data center load in PJM's 13-state footprint would carry its own network-upgrade cost, and the overrun risk attached to it, instead of sharing it with the rate base.
- The proposal also writes a new load category into PJM's rules.
PJM Interconnection asked FERC to approve a combined study process that would cut the time to connect a power plant or data center to its grid from two years to 12 months.
Data Center Dynamics reported the filing Nov. 20. The filing merges the separate studies PJM runs for generation, transmission and large loads. PJM says planning the three together identifies where and how the network must be upgraded for new data center demand. States and utilities would also get clear information on the transmission costs a data center load drives, so they can charge the operator directly instead of spreading the cost across the ratepayer base.
A data center load in PJM's 13-state footprint would carry its own network-upgrade cost, and the overrun risk attached to it, instead of sharing it with the rate base. Leases and PPAs signed before the filing will need to specify who absorbs those upgrades.
“Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers,” PJM spokesman Jeff Shields said.
The proposal also writes a new load category into PJM's rules. Large computational loads, defined as facilities of 50MW or more, would have to stay connected to the grid during routine transmission disturbances. The requirement follows a July incident in which almost 3.9GW of data center load disconnected.
PJM projects electricity requirements from data centers across its Midwest and Mid-Atlantic territory will triple by 2030, to 29GW. In August, the grid operator proposed that new data center customers of 50MW or more pay for the new generation their facilities need.
Private Wealth Daily reported Nov. 17 on the Fast Energization Process, a one-year large-load study plan PJM filed at FERC that would study load and generation together in about half the time. PJM wants a 60-day comment period on its proposal and a FERC ruling within 120 days.
PJM's plan halves the hookup wait and moves upgrade costs
Current PJM rules versus the process filed at FERC on Nov. 20
Today
2 years
- Study process
- Three separate studies
- Who pays for upgrades
- Ratepayers at large
Proposed
12 months
- Study process
- One combined study
- Who pays for upgrades
- The data center operator
Show as table
| Today | Proposed | |
|---|---|---|
| Figure | 2 years | 12 months |
| Study process | Three separate studies | One combined study |
| Who pays for upgrades | Ratepayers at large | The data center operator |
Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers.Jeff Shields, PJM spokesman
Reported by the Energy Transition desk from Data Center Dynamics, Private Wealth Daily archive, PJM filing to FERC, US Senate vote and Google/Ohio Power upgrade. Published . Updated Nov 20, 2026 · 2:24 p.m. ET. Corrections