PJM asks FERC to cut grid connection times to 12 months

The proposal would study generation, transmission and large loads together and let states charge data center operators directly for the upgrades they drive.

At a glance

  1. Data Center Dynamics reported the filing Nov. 20.
  2. A data center load in PJM's 13-state footprint would carry its own network-upgrade cost, and the overrun risk attached to it, instead of sharing it with the rate base.
  3. The proposal also writes a new load category into PJM's rules.

PJM Interconnection asked FERC to approve a combined study process that would cut the time to connect a power plant or data center to its grid from two years to 12 months.

Data Center Dynamics reported the filing Nov. 20. The filing merges the separate studies PJM runs for generation, transmission and large loads. PJM says planning the three together identifies where and how the network must be upgraded for new data center demand. States and utilities would also get clear information on the transmission costs a data center load drives, so they can charge the operator directly instead of spreading the cost across the ratepayer base.

A data center load in PJM's 13-state footprint would carry its own network-upgrade cost, and the overrun risk attached to it, instead of sharing it with the rate base. Leases and PPAs signed before the filing will need to specify who absorbs those upgrades.

“Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers,” PJM spokesman Jeff Shields said.

The proposal also writes a new load category into PJM's rules. Large computational loads, defined as facilities of 50MW or more, would have to stay connected to the grid during routine transmission disturbances. The requirement follows a July incident in which almost 3.9GW of data center load disconnected.

PJM projects electricity requirements from data centers across its Midwest and Mid-Atlantic territory will triple by 2030, to 29GW. In August, the grid operator proposed that new data center customers of 50MW or more pay for the new generation their facilities need.

Private Wealth Daily reported Nov. 17 on the Fast Energization Process, a one-year large-load study plan PJM filed at FERC that would study load and generation together in about half the time. PJM wants a 60-day comment period on its proposal and a FERC ruling within 120 days.

PJM's plan halves the hookup wait and moves upgrade costs

Current PJM rules versus the process filed at FERC on Nov. 20

Today

2 years

Study process
Three separate studies
Who pays for upgrades
Ratepayers at large

Proposed

12 months

Study process
One combined study
Who pays for upgrades
The data center operator
Source: PJM filing, via Data Center Dynamics
Show as table
TodayProposed
Figure2 years12 months
Study processThree separate studiesOne combined study
Who pays for upgradesRatepayers at largeThe data center operator
Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers.Jeff Shields, PJM spokesman

Reported by the Energy Transition desk from Data Center Dynamics, Private Wealth Daily archive, PJM filing to FERC, US Senate vote and Google/Ohio Power upgrade. Published . Updated Nov 20, 2026 · 2:24 p.m. ET. Corrections

Related

Infrastructure

Exelon weighs $3 billion to $7 billion for regulated storage

The range covers 1.5 GW to 3.5 GW and excludes a $1 billion, 500-MW project with Invenergy awaiting a New Jersey decision.

Infrastructure

Winter reliability now rides on interregional transfers

Peak outages fell sharply from Elliott and Uri; FERC/NERC credit coordination and transfers, not new steel.

Infrastructure

PJM files one-year large-load study plan at FERC

The Fast Energization Process would study load and generation together in about half the time while FERC weighs network upgrade costs.

Infrastructure

Budderfly plans $500 million in municipal energy financing

The energy-as-a-service firm becomes the utility customer of record and is paid from bill savings over 15-year contracts.

Infrastructure

UK sets £1 notional budget for offshore wind in AR8

Fixed-bottom offshore wind keeps its £113/MWh strike price and Pot 5 is left at zero while ministers set Pots 1 to 4 after reviewing bids.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections