At a glance
- Ministers will review anonymized bids across Pots 1 to 4 before deciding whether to raise those budgets.
- The clearest parameter for bidders is the administrative strike price for fixed-bottom offshore wind: £113 per MWh in 2024 prices, unchanged from AR7, according to BVG Associates.
- Almost 17 GW of fixed-bottom capacity is eligible to compete in AR8, BVG Associates estimates.
The UK set a nominal initial budget of £1 for offshore wind in Allocation Round 8, its next contracts for difference auction, and left Pot 5 for tidal stream and wave at zero for the round.
Ministers will review anonymized bids across Pots 1 to 4 before deciding whether to raise those budgets. Any additional funding depends on the bids offering value for money for consumers and on agreement with HM Treasury. The £1 notional figure, announced by the Department for Energy Security and Net Zero on Nov. 19, applies to solar, onshore wind and floating and deepwater offshore wind as well. Fixed-bottom offshore wind projects compete in Pot 3, while floating and other deepwater projects sit in Pot 4.
The clearest parameter for bidders is the administrative strike price for fixed-bottom offshore wind: £113 per MWh in 2024 prices, unchanged from AR7, according to BVG Associates. For developers and their lenders, that means pricing a bid in full before the government decides how much capacity the budget will support.
Almost 17 GW of fixed-bottom capacity is eligible to compete in AR8, BVG Associates estimates. The consultancy expects bids to total around 10 GW to 12 GW and estimates that between 2 GW and 5 GW could ultimately secure contracts.
Pot 5, which covers emerging and smaller technologies such as tidal stream and wave energy, was set at zero, a decision the government said was final for AR8. “We recognise the longer-term potential of key emerging technologies, but AR8 must prioritise affordability and strategic technologies capable of delivering clean power at scale in the near term,” the government said on a website dedicated to CfD allocation.
AR8 keeps separate clearing-price groups for Scottish projects and those in the rest of Great Britain, a design BVG Associates said recognizes regional differences in project costs and improves budget efficiency. Final budget decisions for Pots 1 to 4 are expected in early 2027, after the bid review.
Most eligible capacity may go uncontracted
Fixed-bottom offshore wind capacity eligible to compete and likely to secure contracts in AR8, GW
Eligible to bid
17 GW
Likely to win
2–5 GW
BVG expects bids of 10–12 GW, with the £1 budget set only after ministers review them.
Reported by the Energy Transition desk from offshoreWIND.biz. Published . Corrections