PJM files one-year large-load study plan at FERC

The Fast Energization Process would study load and generation together in about half the time while FERC weighs network upgrade costs.

At a glance

  1. Most major US grid operators filed proposals the same day.
  2. PJM calls the plan the Fast Energization Process and says the one-year combined study is about twice as fast as its current cycle, according to Utility Dive, which first reported the filings.
  3. For developers and the funds behind them, a one-year combined study roughly halves the time a project carries an unknown network upgrade bill.

PJM Interconnection filed a proposal at FERC on Monday to study large loads such as data centers together with generation requests in a single one-year process. Most major US grid operators filed proposals the same day. FERC's June show-cause orders said their existing rules for large loads appeared inadequate and asked them to propose reforms or defend the current approach.

PJM calls the plan the Fast Energization Process and says the one-year combined study is about twice as fast as its current cycle, according to Utility Dive, which first reported the filings. The filing lists insufficiently fast interconnection processes, duplicative studies, speculative requests, limited visibility into the drivers of transmission upgrades and a resource adequacy shortfall as the problems it addresses.

For developers and the funds behind them, a one-year combined study roughly halves the time a project carries an unknown network upgrade bill. The reform as drafted would also settle co-location and behind-the-meter rules, the terms that decide whether an on-site generator can serve a load without going through the full interconnection queue.

The orders set out five issues, including cost-shift prevention, transparent transmission costs, and co-location and behind-the-meter rules. They also asked for efficient study processes and alternative transmission technologies, new transmission services for flexible large loads, and a study process for generating facilities serving electrically proximate and co-located loads.

Proposals that assign network upgrade costs to the load that causes them, rather than spreading them across a transmission zone, would change project economics more than a faster study does. FERC's orders respond to a surge in data center development and to concerns that existing utility customers will pay for some of the infrastructure built for data centers.

PJM's companion proposal requires large computational loads to ride through grid disturbances rather than tripping off and dropping demand. That makes a large load behave more like firm capacity and less like a load that vanishes during a fault, which matters to a grid operator balancing a system with less dispatchable generation.

SPP is slated to file its proposal by Friday, and FERC will next decide whether the one-year study survives as filed or is set for hearing and settlement.

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

SPP's Western adequacy stop-gap draws protests, including from its own market monitor

WAPA, Basin Electric and Guzman Energy seek changes to the Sept. 4 proposal, which would run until mandatory adequacy rules take effect on June 1, 2027.

Infrastructure

FERC's LaCerte says building more can fix power affordability

The Republican commissioner, confirmed through 2031, wants more Congressional hearings and says gas should reach regions that need it.

Infrastructure

Exelon weighs $3 billion to $7 billion for regulated storage

The range covers 1.5 GW to 3.5 GW and excludes a $1 billion, 500-MW project with Invenergy awaiting a New Jersey decision.

Infrastructure

Siemens Energy backlog hits €164 billion on turbine orders

US orders rose 70% in fiscal 2026 while data centers supply less than 10% of the order book.

Infrastructure

Google signs 50MW geothermal PPA with Quaise Energy

Project Obsidian near Bend, Oregon, starts supplying Google's The Dalles data centers in 2030 and could scale to 250MW.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

PJM files one-year large-load study plan at FERC