At a glance
- Most major US grid operators filed proposals the same day.
- PJM calls the plan the Fast Energization Process and says the one-year combined study is about twice as fast as its current cycle, according to Utility Dive, which first reported the filings.
- For developers and the funds behind them, a one-year combined study roughly halves the time a project carries an unknown network upgrade bill.
PJM Interconnection filed a proposal at FERC on Monday to study large loads such as data centers together with generation requests in a single one-year process. Most major US grid operators filed proposals the same day. FERC's June show-cause orders said their existing rules for large loads appeared inadequate and asked them to propose reforms or defend the current approach.
PJM calls the plan the Fast Energization Process and says the one-year combined study is about twice as fast as its current cycle, according to Utility Dive, which first reported the filings. The filing lists insufficiently fast interconnection processes, duplicative studies, speculative requests, limited visibility into the drivers of transmission upgrades and a resource adequacy shortfall as the problems it addresses.
For developers and the funds behind them, a one-year combined study roughly halves the time a project carries an unknown network upgrade bill. The reform as drafted would also settle co-location and behind-the-meter rules, the terms that decide whether an on-site generator can serve a load without going through the full interconnection queue.
The orders set out five issues, including cost-shift prevention, transparent transmission costs, and co-location and behind-the-meter rules. They also asked for efficient study processes and alternative transmission technologies, new transmission services for flexible large loads, and a study process for generating facilities serving electrically proximate and co-located loads.
Proposals that assign network upgrade costs to the load that causes them, rather than spreading them across a transmission zone, would change project economics more than a faster study does. FERC's orders respond to a surge in data center development and to concerns that existing utility customers will pay for some of the infrastructure built for data centers.
PJM's companion proposal requires large computational loads to ride through grid disturbances rather than tripping off and dropping demand. That makes a large load behave more like firm capacity and less like a load that vanishes during a fault, which matters to a grid operator balancing a system with less dispatchable generation.
SPP is slated to file its proposal by Friday, and FERC will next decide whether the one-year study survives as filed or is set for hearing and settlement.
Reported by the Energy Transition desk from Utility Dive. Published . Corrections