AEP raises five-year capital plan to $100B on data center load

Contracted large load rose 22% to 84 GW, led by a 10.4-GW Ohio campus SB Energy is developing.

$100BAEP's five-year capital plan after a 30% increase

At a glance

  1. Through 2031 the plan allocates $20 billion to gas-fired generation and $37 billion to transmission, up from $13 billion and $33 billion under the previous plan, according to company presentations.
  2. For allocators weighing wires against generation, the Ohio lines carry a formula-set return while the fuel cells depend on a single 20-year offtake.
  3. AEP expects to start building the Ohio project, Piketon, early next year.

American Electric Power raised its five-year capital plan to $100 billion from $78 billion, a 30% increase driven by expected generation and transmission spending, company officials said on an earnings call Wednesday, Utility Dive reported.

Contracted large load rose 22% to 84 GW, mainly on a 10.4-GW data center campus in Ohio that SB Energy is developing, CFO Trevor Mihalik said on the call. Through 2031 the plan allocates $20 billion to gas-fired generation and $37 billion to transmission, up from $13 billion and $33 billion under the previous plan, according to company presentations. AEP’s utilities also expect to spend $8 billion on renewable projects over the next five years.

For allocators weighing wires against generation, the Ohio lines carry a formula-set return while the fuel cells depend on a single 20-year offtake. SoftBank and its affiliates will pay for the Ohio transmission project built for SB Energy’s campus, and the lines earn an 11.35% base return on equity, adjustable to 11.99% or 10.71% with final costs and in-service dates, AEP said in its quarterly SEC filing. The Wyoming fuel cell project, 702 MW of Bloom Energy units at a cost of $4 billion, is underpinned by a 20-year power purchase agreement with Google and is due online in 2028.

“Contracted customer demand is growing faster than the operating output of our existing fleet, creating a clear durable need for new baseload dispatchable generation,” Mihalik said on the call.

AEP expects to start building the Ohio project, Piketon, early next year. Its three 765-kV lines will each provide about 3.2 GW of capacity for the data center complex, with targeted in-service dates of Dec. 31, 2028, 2029 and 2030, the company said in its quarterly SEC filing. The campus’s initial 800 MW of load will be served on existing transmission capacity and does not require additional regulatory approvals; the transmission project needs approvals from PJM Interconnection, the Public Utilities Commission of Ohio and the Federal Energy Regulatory Commission.

Gas-fired generation adds $7 billion to the plan, compared with $4 billion for transmission, and AEP’s utilities are preparing to add about 9 GW of gas-fired generation. Google, whose contract underpins the Wyoming fuel cells, has also paid directly for grid capacity behind its own load, agreeing to fund the Arkansas grid for a 600 MW data center, as Private Wealth Daily previously reported.

Gas spending rose 54%; transmission rose 12%

AEP five-year capital plan by category, prior plan vs. new plan ($B)

Transmission $33BGas-fired generation $13B$37B$20BPrior planNew planTransmission $33BGas-fired generation $13B$37B$20BPrior planNew planTransmission $33BGas-fired generat… $13B$37B$20BPrior planNew plan
Source: Company presentations via Utility Dive
Show as table
ItemPrior planNew planChange
Gas-fired generation$13B$20B+$7B
Transmission$33B$37B+$4B
Contracted customer demand is growing faster than the operating output of our existing fleet, creating a clear durable need for new baseload dispatchable generation.Trevor Mihalik, AEP executive vice president and CFO

Reported by the Fundraising desk from Utility Dive. Published . Corrections

Related

Infrastructure

NERC stakeholders back draft reliability rules for 50MW-plus compute loads

The draft covers AI data centers and crypto miners at 50 MW or more and 100 kV or above, and it now moves to the NERC board and then FERC.

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

AEP to buy up to 1.6 GW Mainspring units, plans $4B Cheyenne fuel cells

The eight-year Mainspring agreement has a stated ceiling of up to $4 billion, while the planned 702-MW Cheyenne project pairs Bloom Energy fuel cells with a 20-year Google PPA.

Infrastructure

Foundation Credit closes $540M infrastructure debt fund above target

The close came a week after Foundation Credit announced a majority investment from New Holland Capital.

Infrastructure

EdgeCore closes $521 million green ABS on Santa Clara campus

The 36MW SV01 data center backs the deal, EdgeCore's second securitization, which is more than double last year's $235 million Phoenix issue.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections