NERC stakeholders back draft reliability rules for 50MW-plus compute loads

The draft covers 50 MW-plus AI data centers and crypto miners at 100 kV or above; the next step is the NERC board, then FERC.

At a glance

  1. The draft applies to computational loads of 50 megawatts or more connected at 100 kilovolts and above, and it names both AI data centers and crypto miners as targets.
  2. A 50 MW crypto site and a 50 MW AI campus would fall into the same bucket; the test is the load's size and connection voltage, not the operator.
  3. AEP agreed to buy up to 1.6 GW of Mainspring units under an eight-year agreement with a stated ceiling of up to $4 billion.

NERC stakeholders approved draft reliability standards for large computational loads, advancing rules that would cover AI data centers and crypto miners toward federal review. The draft applies to computational loads of 50 megawatts or more connected at 100 kilovolts and above, and it names both AI data centers and crypto miners as targets. A 50 MW crypto site and a 50 MW AI campus would fall into the same bucket; the test is the load's size and connection voltage, not the operator. The next step is the NERC board; if adopted there, the rules go to FERC. The stakeholder vote moves the draft forward without making it final.

AEP agreed to buy up to 1.6 GW of Mainspring units under an eight-year agreement with a stated ceiling of up to $4 billion. It also plans a $4 billion Cheyenne project pairing a 702 MW Bloom Energy fuel-cell installation with a 20-year Google power purchase agreement. Actis added 244 MW of Polish battery storage from DRI: the Kozienice site is acquired and construction-ready, while Trzebinia is signed and completes once operational.

Reported by The Wrap desk from Private Infrastructure Daily records. Published . Corrections

Private Wealth Daily member access

Continue this analysis

Get the complete Infrastructure analysis and every detail that follows.

Enter a valid work email to continue reading.

Private Infrastructure Daily, from Private Wealth Daily. Unsubscribe anytime.

Full featuresIn-depth analysis and exclusive reporting.
Source-backed contextEvidence, context and the complete story.
One login across the networkAccess every Daily Network publication.

Related

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

Uruguay signs $5.7bn Solaria deal for up to 500MW of solar-paired capacity

Phase one pairs a 200MW data center with a 350MW solar project and is due in 2029, according to the newsroom's data basis.

Infrastructure

Washington's grid money stops buying new corridors

The $1.9 billion SPARK package buys 23 gigawatts on lines that already exist, turning the data center buildout's power schedule into a question of tariff design.

Infrastructure

Google and Voltus expand PJM virtual power plant to 1,170 MW

The expansion adds 1,070 MW to the June 100 MW program, with a three-to-four-year ramp and a 2040 term.

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported $45 billion contract would double Anthropic's committed capacity at Monarch to 920MW; Microsoft already holds 1.35GW there.

From other sections