UK rejects Drax-backed bid to power 1.2GW data center with biomass

The Selby application failed AI Growth Zone selection criteria; Drax has pivoted to a 100MW project on grid power.

At a glance

  1. The application was filed by North Yorkshire Council, the University of York and Drax, and proposed a 1.2GW data center running off the site’s 2.58GW bioenergy plant, which the report describes as the UK’s single largest energy generator.
  2. According to the York Press, the bid failed selection criteria including “credible plans for energy delivery, environmental considerations, and local economic benefit.”
  3. The applicants described the facility as the world’s largest “carbon negative data center.”

The UK government has rejected a North Yorkshire bid to power an AI data center from Drax’s biomass plant near Selby, Data Center Dynamics reported on Oct. 16.

The application was filed by North Yorkshire Council, the University of York and Drax, and proposed a 1.2GW data center running off the site’s 2.58GW bioenergy plant, which the report describes as the UK’s single largest energy generator.

According to the York Press, the bid failed selection criteria including “credible plans for energy delivery, environmental considerations, and local economic benefit.” The scheme lets local authorities apply for state funding and other benefits for large-scale AI data centers, and the rejection was a selection decision under it rather than a planning refusal.

The applicants described the facility as the world’s largest “carbon negative data center.” That claim rested on installing chemical scrubbers in partnership with Mitsubishi Heavy Industries and capturing at least eight million tonnes of CO2 from the chimneys each year.

The plant itself is one of the UK’s largest emitters: Ember put Drax’s 2025 emissions at 14.1 million tonnes of CO2 equivalent, meaning the capture the applicants claimed would cover a bit more than half of that.

Drax pivots to a 100MW grid-fed project

Drax has pivoted to a 100MW front-of-meter data center that would draw power from the national grid rather than from the plant.

A Drax spokesperson told the York Press the company was pleased to support York and North Yorkshire’s AI Growth Zone bid and had “never relied” on its success.

The company said the first phase would be submitted to planning authorities “in the coming months,” and that successful progress could enable a data center to come online before the end of this decade.

Drax’s interest in the site dates back to November 2024, when it was reported to be in discussions with operators about co-locating a data center with biomass generation. The report also notes Drax has since signed a ten-year corporate power purchase agreement with Global Switch to support the firm’s UK operations.

The rejected scheme would have put 1.2GW of load behind the meter at Drax’s plant; the replacement takes 100MW from the grid and has not yet secured planning approval.

Rejected 1.2GW data center vs. the 100MW replacement Drax now plans

  • Drax power station capacity2.6K MW
  • Rejected behind-the-meter data center1.2K MW
  • Replacement grid-fed data center100 MW
Source: Data Center Dynamics · Oct 2026
Show as table
ItemValue (MW)
Drax power station capacity2.6K MW
Rejected behind-the-meter data center1.2K MW
Replacement grid-fed data center100 MW

Reported by the Data centers & fiber desk from Data Center Dynamics and York Press (quoted in Data Center Dynamics). Published . Corrections

Related

Infrastructure

Uruguay signs $5.7bn Solaria deal for up to 500MW of solar-paired capacity

Phase one pairs a 200MW data center with a 350MW solar project and is due in 2029, according to the newsroom's data basis.

Infrastructure

DigiCo signs 71MW Sydney data center lease, taking SYD1 to fully leased

The 15-year agreement includes 20MW reassigned from capacity already under contract at the facility.

Infrastructure

Global Switch to host Nvidia Blackwell deployment in Paris, tenant unnamed

Global Switch names no tenant or scale for a liquid-cooled Nvidia DGX-ready build it calls one of Europe's biggest Blackwell deployments.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections