DigiCo signs 71MW Sydney data center lease, taking SYD1 to fully leased

The 15-year agreement includes 20MW reassigned from capacity already under contract at the facility.

At a glance

  1. The agreement carries what DigiCo describes as investment-grade credit support and brings the facility to fully leased across the 88MW it will hold once current upgrades and expansions are complete.
  2. Not all of the 71MW is new demand: 20MW was already contracted at the site and is being reallocated to the new customer, while the remaining 17MW of the 88MW is leased to colocation customers.
  3. DigiCo expects the first 10MW of the SYD1 Expansion to be energized and income-producing in late Q4 FY27, with the balance delivered progressively over FY28.

DigiCo Infrastructure REIT has signed a 15-year contract for 71MW of capacity at its SYD1 data center in Sydney with an unnamed global technology firm, the ASX-listed company said this week. The agreement carries what DigiCo describes as investment-grade credit support and brings the facility to fully leased across the 88MW it will hold once current upgrades and expansions are complete.

Not all of the 71MW is new demand: 20MW was already contracted at the site and is being reallocated to the new customer, while the remaining 17MW of the 88MW is leased to colocation customers.

"Execution of the 71MW contract at SYD1 is a key milestone for DGT, taking the site to 100 percent contracted across 88MW of total capacity," said Simon Mitchell, co-head and CFO of DGT.

DigiCo expects the first 10MW of the SYD1 Expansion to be energized and income-producing in late Q4 FY27, with the balance delivered progressively over FY28.

The Sydney facility reached DigiCo through HMC Capital, which acquired Global Switch's Australian business in 2024 and then floated DigiCo to hold its data center assets, including the Ultimo site. Mitchell said the original plan was to fully lease and develop SYD1 to 88MW over five years, and DigiCo now expects to reach that milestone ahead of plan.

Only 51MW of DigiCo's 71MW SYD1 lease is new demand

SYD1 at completion, by how the 88MW is contracted

  • New capacity to global technology firm51 MW
  • Reallocated from existing contract20 MW
  • Other colocation customers17 MW
Source: DigiCo statement via Data Center Dynamics
Show as table
ItemValue (MW)
New capacity to global technology firm51 MW
Reallocated from existing contract20 MW
Other colocation customers17 MW

One counterparty, most of the site

Reallocating 20MW to the new customer leaves 71 of the site's 88MW contracted to one unnamed counterparty on a 15-year term, concentrating the facility's revenue behind one credit. The credit backing is described only as investment grade. Global Switch named no tenant for the liquid-cooled Nvidia deployment it announced for Paris in late September, per this publication's reporting.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

UK rejects Drax-backed bid to power 1.2GW data center with biomass

The Selby application failed AI Growth Zone selection criteria; Drax has pivoted to a 100MW project on grid power.

Infrastructure

Global Switch to host Nvidia Blackwell deployment in Paris, tenant unnamed

Global Switch names no tenant or scale for a liquid-cooled Nvidia DGX-ready build it calls one of Europe's biggest Blackwell deployments.

Infrastructure

The SPAC's collateral is a grid queue position

Blue Acquisition Corp's 15-year CoreWeave lease on a Niagara cryptomine prices a decommissioned power plant's connection at AI rates, making the tenant's contract stack the publicly traded collateral.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections