Senate passes 62-33 bill to shift grid costs onto data centers

The bill would apply FERC-set protections to projects above 20MW and expand federal authority over interstate transmission permits.

At a glance

  1. Sponsored by Senator Shelley Moore Capito, Republican of West Virginia, the bill passed after the Senate voted 73-25 to advance the permitting bill on Nov. 10, as Private Infrastructure Daily previously reported.
  2. For a developer underwriting a campus above 20MW, the bill moves a larger share of grid infrastructure cost onto the project, with FERC to set the size.
  3. FERC is weighing a PJM proposal to cut grid connection times to 12 months, which would let states charge data center operators directly for the upgrades they drive, as Private Infrastructure Daily previously reported.

The Senate passed the Bipartisan American Affordability and Jobs Act 62-33, directing the Federal Energy Regulatory Commission to make data centers above 20MW pay a greater share of the grid infrastructure their electricity consumption requires.

Sponsored by Senator Shelley Moore Capito, Republican of West Virginia, the bill passed after the Senate voted 73-25 to advance the permitting bill on Nov. 10, as Private Infrastructure Daily previously reported.

For a developer underwriting a campus above 20MW, the bill moves a larger share of grid infrastructure cost onto the project, with FERC to set the size. Projects at or below 20MW fall outside the protections.

FERC is weighing a PJM proposal to cut grid connection times to 12 months, which would let states charge data center operators directly for the upgrades they drive, as Private Infrastructure Daily previously reported.

Beyond cost allocation, the bill would expand FERC's authority to issue construction permits for certain interstate transmission projects and shorten deadlines for federal environmental reviews. An interconnection date sets when a project starts earning, so the procedural changes affect developer timelines.

It would also narrow the circumstances in which environmental permits can be revoked or challenged in court, accelerate renewable, geothermal, hydropower and offshore energy projects, and remove permit requirements for onshore oil and gas drilling on non-federal land.

Environmental groups say the bill risks damage by making fossil fuel infrastructure easier to build, according to Data Center Dynamics. Earth Justice said in a statement, “The bill exempts a wide array of government actions from NEPA, including loans, loan guarantees, and pipeline expansions within existing rights-of-way.”

The bill now goes to the House of Representatives. If it passes there without changes, it goes to the President.

The bill exempts a wide array of government actions from NEPA, including loans, loan guarantees, and pipeline expansions within existing rights-of-way.Earth Justice, in a statement reported by Data Center Dynamics

Reported by the Data centers & fiber desk from Data Center Dynamics, Private Infrastructure Daily archive and Private Infrastructure Daily archive. Published . Corrections

Related

Infrastructure

PJM asks FERC to cut grid connection times to 12 months

The proposal would study generation, transmission and large loads together and let states charge data center operators directly for the upgrades they drive.

Infrastructure

PJM files one-year large-load study plan at FERC

The Fast Energization Process would study load and generation together in about half the time while FERC weighs network upgrade costs.

Infrastructure

FERC's LaCerte says building more can fix power affordability

The Republican commissioner, confirmed through 2031, wants more Congressional hearings and says gas should reach regions that need it.

Infrastructure

Apollo-backed Vaultica among bidders for Retelit data centers

Ardian, Macquarie and Rai Way also submitted non-binding offers for the 38 Italian data centers plus an Austrian site, valued at about €700 million.

Infrastructure

CyrusOne and KEPCO top out 48MW Osaka data center

OSK1's first phase is due online in the first quarter of 2028.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections