CyrusOne and Kansai Electric Power Co. said this week that OSK1, their first data center in Japan, has topped out its steel structure at an Osaka site planned for 48MW of IT capacity.
The companies marked the milestone with a Jōtōshiki ceremony, in which gold and silver bolts are driven into the final steel beam. Ground was broken in September 2024. The first phase is due online in the first quarter of 2028.
Osaka's 48MW is 8% of the venture's 600MW IT capacity target, leaving roughly a dozen more facilities of comparable capacity to reach the goal. The joint venture, announced in May 2023, has said it will invest at least ¥1 trillion ($7 billion) over the next decade and targets 900MW of business scale.
CyrusOne, owned by KKR, operates or is developing more than 40 data centers across the US and Europe. Osaka is its first expansion into Asia. KEPCO owns generation plants totaling more than 35GW and controls ISP Optage and real estate developer Kanden. The venture has said it aims to develop in Tokyo and other major Japanese markets.
Osaka's 48MW is 8% of the venture's 600MW goal
Planned IT capacity at OSK1 against the joint venture's 600MW IT capacity target, in MW
- Actual
- Target
- OSK1, Osaka48 MW of 600 MW · 8%
Show as table
| Item | Actual | Target | Of target |
|---|---|---|---|
| OSK1, Osaka | 48 MW | 600 MW | 8% |
Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections