Pennsylvania puts a 2030 date on PJM's capacity shortfall

A Pennsylvania study models 13.20 loss-of-load days in 2030 and a reference case nearly six times the planning criterion, making firm capacity and grid position the scarce assets and leaving merchant renewables exposed.

At a glance

  1. Utility Dive first reported the findings.
  2. The reference case is the one capital should read twice.
  3. Steve DeFrank, the commission's chairman, said in a statement accompanying the release that demand and supply are out of balance and the status quo is unsustainable, and that urgent action is needed at PJM and across Pennsylvania so electricity supply keeps pace with demand.

A study commissioned by the Pennsylvania Public Utility Commission has put a number on what data-center load growth does to PJM's grid: in the worst case the regional planning standard stops functioning, with a modeled 2030 loss-of-load expectation of 13.20—more than thirteen days a year when the system cannot serve all the load on it, or more than a hundred times the criterion PJM uses to keep shortages to roughly one event a decade. Utility Dive first reported the findings.

The reference case is the one capital should read twice. Running PJM's own 2026 load forecast, with no unusual assumptions about how much supply actually arrives, the study lands on a modeled 2030 loss-of-load expectation of 0.59, nearly six times the planning criterion; the breach sits in the model's middle. The gap owes largely to surging data-center additions—the demand side of PJM's queue moving faster than the supply side can be permitted, financed, and energized.

Modeled 2030 PJM shortfall: 13.2 days a year in the worst case

Loss-of-load expectation, days per year; PJM's criterion is about 0.1

0.1 days/yearPJM planning criterion0.59 days/yearReference case (2026 load forecast)13.2 days/yearWorst case0.1 days/yearPJM planning criterion0.59 days/year13.2 days/yearWorst case0.1 days/yearPJM planning criterion0.59 days/year13.2 days/yearWorst case
Source: PA PUC-commissioned PJM reliability study · via Utility Dive
Show as table
LabelValue (days/year)
PJM planning criterion0.1 days/year
Reference case (2026 load forecast)0.59 days/year
Worst case13.2 days/year

The baseline is already a breach

Steve DeFrank, the commission's chairman, said in a statement accompanying the release that demand and supply are out of balance and the status quo is unsustainable, and that urgent action is needed at PJM and across Pennsylvania so electricity supply keeps pace with demand. PJM's own response to CBS affiliate WJAC was that it has taken a number of actions to increase supply and manage new demand in line with the Ratepayer Protection Pledge that data center developers have signed to shield residential customers and other ratepayers from the reliability and cost consequences of their load. That pledge is the closest thing in the record to a rule about how new load must behave, and it is a developer's concession in advance that the residential class will not be asked to carry the cost.

Pennsylvania remains a net energy exporter in the reference case, but exports shrink from about 91 TWh in 2025 to 69 TWh by 2035 and 38 TWh by 2040; in the high-load, low-supply scenario the state becomes a net importer of 5 TWh by 2040. The report's own language suggests even that framing is generous, because large unmet load in 2031 and later years means some of the 2035 and 2040 load is likely to go unserved, with not enough regional generation to meet PJM-wide requirements.

For a decade the PJM story for investors has been the interconnection queue—who holds a position and how long it takes to energize—but the study moves the binding constraint from the queue to adequacy. As this publication has argued, connection rights now trade before electrons do; the corollary this document adds is that a connection right without firm capacity behind it is a promise the region may not be able to keep. The scarce asset is dispatchable generation and an energized position on a constrained grid, not a nameplate megawatt of merchant renewable capacity.

The study sets a floor under the value of firm, dispatchable capacity and grid position in PJM by showing the shortfall arriving inside a planning horizon with a fixed date attached rather than at its far edge. The house view, firm power repricing as the transition's scarce asset and renewables margins under pressure until contracts replace merchant exposure, finds its mechanism here: a reliability gap that has to be closed by a date. Assets selected to close an adequacy gap are chosen less by merchant economics than by what can be permitted and energized in time.

Lenders are the second-order story. A PJM position underwritten as a merchant energy asset reads as a reliability asset in the study's framing, and reliability value attaches to the years the criterion is breached rather than to average capture of a spot price. The financing question the study raises is whether a project's revenue case still holds if the shortage it is meant to serve is met first by administrative curtailment, since curtailment does not clear at a price that reaches a project's income statement.

Pennsylvania is already trying to spend its permitting leverage on supply. Last month Governor Josh Shapiro issued an executive order offering preferential permitting to data center projects with peak demand above 25 MW if they commit to certain requirements, including sourcing their electricity from new power supplies—a direct attempt to make new load bring new generation with it, treating consent, the permit, the interconnection, the state's yes, as the commodity that decides what gets built.

There is also the part of last Thursday's unanimous PUC vote that capital should read as risk. Alongside a motion on data center development and ratemaking, the commission directed its staff to propose updates to the state's emergency curtailment rules and to organize a technical conference. Emergency curtailment is how a system serves an unmet balance when there is not enough generation to go around: the operator sheds load by instruction. That is the scenario no merchant revenue forecast contains, an adequacy event that resolves administratively, with which load is shed decided by rule.

That makes a developer underwriting merchant solar or storage inside PJM on current revenues an underwriter of an asset the adequacy gap puts at risk. The date to watch is the technical conference and the curtailment rulemaking that follows it, because that is where Pennsylvania decides whether data-center load pays for the generation it needs, or whether the residential class keeps the bill and the region keeps the risk.

Pennsylvania's net exports shrink to zero by 2040 in the high-load case

Net electricity exports, terawatt-hours

  • Inflow / above zero
  • Outflow / below zero
+91 TWh2025 · reference+69 TWh2035 · reference+38 TWh2040 · reference−5 TWh2040 · high-load, low-supply+91 TWh2025 · reference+69 TWh+38 TWh−5 TWh2040 · high-load, low-supply+91 TWh2025 · reference+69 TWh+38 TWh−5 TWh2040 · high-load, low-supply
Source: PA PUC-commissioned PJM reliability study · via Utility Dive
Show as table
LabelValue (TWh)
2025 · reference91 TWh
2035 · reference69 TWh
2040 · reference38 TWh
2040 · high-load, low-supply−5 TWh

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

Pennsylvania moves to price grid access for data centers

A curtailment rewrite and a standing cost-of-capital docket will decide which PJM load gets financed, and other state commissions will be reading the order.

Infrastructure

LS Power closes $6bn private equity fund, earmarks $1.7bn for Constellation

COO Darpan Kapadia says demand growth is real and supply will take time to catch up.

Infrastructure

Enverus: SPP leads large-load readiness while PJM holds largest pipeline

SPP has the most advanced framework but about 5% of the high-confidence pipeline; PJM's 11.8 GW is 58% expected to be served behind the meter.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections