Chaince forms AI data center unit with 100MW target

Chaince and Bit Lake plan a 60/40 Texas joint venture starting at 5MW, with definitive documents due within 90 days.

60%Chaince Compute stake in the Texas joint venture

At a glance

  1. The New York-based Nasdaq-listed company announced the wholly owned unit on Nov. 19; it was incorporated in Delaware on Nov. 2.
  2. Chaince Compute is expected to hold 60% of the venture and Bit Lake 40% at the Big Lake, Texas, data center, where Bit Lake operates a 15MW Bitcoin mining facility.
  3. Until the utility letter, interconnection approval and an anchor tenant are in place, the Texas project is a claim on power at a mining site, not a leased AI facility.

Chaince Digital formed Chaince Compute to build US AI data centers at up to 100MW per project and signed a binding framework agreement with Bit Lake for a Texas joint venture, Data Center Dynamics reported. The New York-based Nasdaq-listed company announced the wholly owned unit on Nov. 19; it was incorporated in Delaware on Nov. 2.

Chaince Compute is expected to hold 60% of the venture and Bit Lake 40% at the Big Lake, Texas, data center, where Bit Lake operates a 15MW Bitcoin mining facility. The proposed facility in Reagan County would support AI and high-performance computing workloads. The first phase would use 5MW, subject to written confirmation from utility AEP Texas that the capacity can serve a separate nearby parcel the venture plans to buy. Later phases could reach 25MW by taking 10MW currently mined and another 10MW from BitRealm, subject to interconnection approval and, for the first tranche, an anchor tenant and schedule. The parties aim to sign definitive documents and form the joint venture within 90 days of the Nov. 19 agreement.

Until the utility letter, interconnection approval and an anchor tenant are in place, the Texas project is a claim on power at a mining site, not a leased AI facility. The 5MW first phase depends on the utility letter. The expansions depend on interconnection approval and a named tenant. The joint venture itself depends on definitive documents not yet signed. Chaince Compute is expected to lead financing and tenant recruitment, the two functions that determine whether the 5MW first phase becomes a 25MW asset. A counterparty committing capital would need to price those functions first.

Chaince plans modular construction targeting build times under 12 months per project, and intends to pair grid power with solar and storage to work around power constraints. It also plans joint ventures with site owners and capacity holders, and to lead tenant negotiations. “Long construction timelines and limited power are among the key bottlenecks facing the industry today,” Shi Qiu, chief executive of both Chaince Digital and Chaince Compute, said in the announcement.

Chaince's AI push follows its exit from Filecoin mining. Chaince Digital, formerly Mercurity Fintech Holding, ran Filecoin mining servers in New Jersey through a third-party data center provider from December 2022, according to its annual filing. Its board approved discontinuing that business in December 2025, and all mining nodes had ceased operations by Sept. 30. Core Scientific, the listed miner, said this month it expects to exit Bitcoin mining by the end of 2026 as it shifts to high-density colocation, a move Private Wealth Daily previously reported.

Phase one covers a fifth of the planned capacity

Power capacity by stage, in MW: first phase plus two expansion blocks

  • Added
  • Taken away
  • Total
  • First phase5 MW
  • Capacity now used for mining+10 MW
  • Capacity from BitRealm+10 MW
  • Plan total25 MW
Source: Data Center Dynamics, citing Chaince's Nov. 23 agreement
Show as table
StepChangeRunning total
First phase5 MW5 MW
Capacity now used for mining+10 MW15 MW
Capacity from BitRealm+10 MW25 MW
Plan total25 MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Chaince and Bit Lake plan 60/40 Texas AI data center JV

The partners would start at a 5MW site and target 100MW, with definitive documents due within 90 days.

Infrastructure

Core Scientific to exit bitcoin mining by end of 2026

The company expects to finish the wind-down in the fourth quarter and enter 2027 as a colocation-only provider.

Infrastructure

CoreWeave's 15-year lease turns a Niagara cryptomine into credit

The anchor deal prices a decommissioned power plant's grid connection at AI rates and makes the tenant's contract stack the collateral.

Infrastructure

Axiata to sell Edotco towers to Macquarie-led group for $1.2bn

Axiata says the combined transactions total MYR11.8 billion ($2.9 billion) and will generate MYR2.2 billion in gross proceeds.

Infrastructure

Wren House to buy GIC's 80% stake in Equinix xScale JV

Equinix keeps 20% and remains operator of the European portfolio, with completion expected in the first quarter of 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections