At a glance
- Definitive documents are due within 90 days of the announcement, which is dated Nov. 23, 2026.
- For allocators, the venture is a pipeline entry rather than an asset to underwrite until definitive documents are signed.
- At 5MW, the initial Texas site is a twentieth of the 100MW target for the unit.
Chaince Compute and Bit Lake plan a 60/40 Texas joint venture to develop AI data center capacity, starting with a 5MW site and targeting 100MW for the unit.
Definitive documents are due within 90 days of the announcement, which is dated Nov. 23, 2026. Terms were not disclosed, including which partner holds the 60% share.
For allocators, the venture is a pipeline entry rather than an asset to underwrite until definitive documents are signed. When they arrive, the 60/40 split will show which partner controls the vehicle and, likely, which one funds the first site.
A twentieth of the target at the first site
At 5MW, the initial Texas site is a twentieth of the 100MW target for the unit. The gap between the two figures is 95MW.
The first phase is small next to capacity already being leased in the sector. KT Cloud has leased the full 60MW at Keppel Data Centre Fund III's Ansan data center in South Korea, a building due for service in 2030.
The capacity goal is the part aimed at infrastructure capital; the site is the part with a location and a size. Between the two sit the documents due in 90 days, which will have to settle how the partners fund the first site, who governs the vehicle and what each side contributes for its share.
Counting 90 days from the Nov. 23 announcement, that deadline falls in February 2027.
Reported by The Wrap desk from Chaince Compute / Bit Lake announcement, Nov. 23, 2026 and KT Cloud / Keppel Data Centre Fund III lease coverage. Published . Corrections