Core Scientific to exit bitcoin mining by end of 2026

The company expects to finish the wind-down in the fourth quarter and enter 2027 as a colocation-only provider.

92.5%colocation share of third-quarter revenue

At a glance

  1. Colocation brought in $215.4 million of $232.9 million in third-quarter revenue, about 92.5%, against $15 million a year earlier.
  2. For allocators, the cash-flow metric is billed capacity: 485 MW at Sept. 30, up from 395 MW at June 30, against 590 MW contracted to CoreWeave across five campuses.
  3. Core Scientific sold 3,374 bitcoin for $286.8 million in the first nine months of 2026 and held 32 bitcoin worth $2.7 million at Sept. 30, against 2,537 at the end of 2025.

Core Scientific expects to leave bitcoin mining by the end of 2026, finishing a shift to high-density colocation for AI workloads that already supplies most of its revenue. "We expect to complete our exit from bitcoin mining by year-end," chief executive Adam Sullivan said on the company's Nov. 5 third-quarter earnings call, as Data Center Dynamics reported.

Colocation brought in $215.4 million of $232.9 million in third-quarter revenue, about 92.5%, against $15 million a year earlier. Mining for its own account fell to $12.3 million from $57.4 million, and hosting third-party miners to $5.2 million from $8.7 million. Together the mining lines produced $17.4 million, down from $66.2 million a year earlier. Chief financial officer Jim Nygaard said the company had nearly 50% fewer miners online at the end of September than at the end of 2025.

For allocators, the cash-flow metric is billed capacity: 485 MW at Sept. 30, up from 395 MW at June 30, against 590 MW contracted to CoreWeave across five campuses. Only billed megawatts feed the $215.4 million of colocation revenue, so delivery schedules, rather than signed contracts, are the variable to underwrite. That also separates contracted AI capacity from capacity actually generating cash: Core Scientific is now paid on the second number.

Core Scientific sold 3,374 bitcoin for $286.8 million in the first nine months of 2026 and held 32 bitcoin worth $2.7 million at Sept. 30, against 2,537 at the end of 2025. Its 10-Q listed mining, electrical and high-performance computing equipment as held for sale; mining and electrical gear had first been earmarked for disposal in the second quarter, and the remaining equipment carried $29.7 million at Sept. 30. The company expects those sales to finish within a year of the assets' initial classification.

Capital expenditures, including land and development rights acquisitions, totaled $985.1 million, and the company held $803.9 million in cash and equivalents at the end of September. Adjusted EBITDA was $133.6 million, up from $41.1 million in the second quarter and $6.5 million a year earlier. Net income was $1.18 billion, against a $144 million loss a year earlier, mainly from a non-cash gain on the revaluation of warrants.

With 590 MW contracted to CoreWeave across five campuses, the tenant's own financial capacity is part of the underwriting. As Private Wealth Daily previously reported, CoreWeave posted $3.66 billion of revenue and a $709 million net loss, and its chief executive said the company would not use unsecured debt at current yields. For Core Scientific, the next checkpoint is the fourth-quarter wind-down. After that, the revenue line rests on billed megawatts and its largest disclosed customer.

We expect to complete our exit from bitcoin mining by year-endAdam Sullivan, chief executive of Core Scientific

Reported by the Data centers & fiber desk from Data Center Dynamics, Private Wealth Daily archive, Data Center Dynamics and Core Scientific. Published . Updated Nov 16, 2026 · 9:14 a.m. ET. Corrections

Related

Infrastructure

Core Scientific closes Polaris deal, expands Muskogee campus to 1.5GW

The $444 million Polaris acquisition delivers 440MW of grid power and 40 acres, letting Core Scientific push its Oklahoma campus to 1.5GW.

Infrastructure

CoreWeave's 15-year lease turns a Niagara cryptomine into credit

The anchor deal prices a decommissioned power plant's grid connection at AI rates and makes the tenant's contract stack the collateral.

Infrastructure

Firmus seeks $3bn in equity and customer prepayments

The Australian neocloud had 916MW of contracted capacity and 46MW running in September, according to the Australian Financial Review

Infrastructure

Orennia estimates 191 GW of planned data center capacity at risk

Exposure after the midterms concentrates in Texas, Ohio and Georgia, where incoming Democratic governors campaigned on restricting construction.

Infrastructure

Optimum skips $102.5m in interest payments on $22bn debt

CSC Holdings has until around Dec. 16 before the missed payment counts as a default, and a steering committee of debtholders is negotiating a restructuring.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections