US data center construction falls to 8.4GW in Q3

October starts of 4.6GW put the fourth quarter on pace for a record, Cleanview says.

At a glance

  1. Cleanview counts 38GW of new construction this year, double the previous year.
  2. For allocators underwriting the buildout, the bill is the number that matters: Cleanview estimates construction announced from January through October could reach $1 trillion when complete.
  3. Texas leads with 9.8GW of new capacity started in the last 12 months, ahead of Virginia at 4.5GW and Louisiana at 2.8GW.

New US data center construction fell to 8.4GW in the third quarter from 11.2GW in a record second quarter, according to Cleanview data reported by Data Center Dynamics on Nov. 18.

Cleanview counts 38GW of new construction this year, double the previous year. October starts reached 4.6GW, the highest since June and nearly double the same month a year earlier. Michael Thomas, Cleanview's founder and CEO, said: "Construction slowed this summer, but developers are still starting data centers at twice last year's pace."

For allocators underwriting the buildout, the bill is the number that matters: Cleanview estimates construction announced from January through October could reach $1 trillion when complete. Cleanview also counts 58GW under construction in the US, which it says will require almost as much power as the 65GW operating today.

Texas leads with 9.8GW of new capacity started in the last 12 months, ahead of Virginia at 4.5GW and Louisiana at 2.8GW. Amazon started the most among developers at 4.6GW, followed by Google at 4.1GW and Meta at 3.9GW. Vantage Data Centers led the rest at 2.8GW, then Stack Infrastructure (2.5GW), QTS (2.1GW), Crusoe (1.8GW) and Related Digital (1.6GW). If October's pace holds through November and December, Cleanview expects the fourth quarter to set a new record.

Three hyperscalers started more than 12GW between them

New US data center capacity started in the last 12 months, by developer (GW)

  • Amazon4.6 GW
  • Google4.1 GW
  • Meta3.9 GW
  • Vantage Data Centers2.8 GW
  • Stack Infrastructure2.5 GW
  • QTS2.1 GW
  • Crusoe1.8 GW
  • Related Digital1.6 GW
Source: Cleanview data via Data Center Dynamics
Show as table
ItemValue (GW)
Amazon4.6 GW
Google4.1 GW
Meta3.9 GW
Vantage Data Centers2.8 GW
Stack Infrastructure2.5 GW
QTS2.1 GW
Crusoe1.8 GW
Related Digital1.6 GW
Construction slowed this summer, but developers are still starting data centers at twice last year's pace.Michael Thomas, founder and CEO of Cleanview

Reported by the Data centers & fiber desk from Data Center Dynamics and Cleanview. Published . Corrections

Related

Infrastructure

Data center project count nearly triples; power is the bottleneck

J.P. Morgan's $697 billion hyperscaler capex estimate sets the pace, but the five-month surge in planned projects will be measured against the grid's ability to power them.

Infrastructure

Data centers pay $18m for Ohio patience

The grants are a rounding error next to grid costs — but they price the input the 85% take-or-pay tariff cannot: community toleration.

Infrastructure

Ireland's nuclear opening is a hedge, not a fix

Dublin wants fission in a decade; data centers need power now.

Infrastructure

Orange seeks partners for 24-pair ReuNION leg to Singapore

Phase one to South Africa, carrying 320 Tbps across 16 fiber pairs, has a provisional launch expected in early 2029.

Infrastructure

CEQA can add years to California data center schedules

DLA Piper partner Andrew Brady writes that the law's anti-segmentation rule ties later phases to the first discretionary approval.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections