At a glance
- The California Energy Commission projects statewide data center demand could reach approximately 4.5 gigawatts by 2040, more than four times the roughly 1 gigawatt it estimates today.
- CEQA, the 1973 statute, requires public agencies to evaluate and publicly disclose environmental impacts before discretionary entitlements can be approved.
- For underwriters, the key provision is anti-segmentation, which requires the whole project and future phases to be analyzed if any part needs a discretionary approval.
Once power and water are settled, the California Environmental Quality Act can add years to a data center schedule and shapes its cost and risk, writes DLA Piper partner Andrew Brady in Data Center Dynamics. The California Energy Commission projects statewide data center demand could reach approximately 4.5 gigawatts by 2040, more than four times the roughly 1 gigawatt it estimates today.
CEQA, the 1973 statute, requires public agencies to evaluate and publicly disclose environmental impacts before discretionary entitlements can be approved. It does not bar projects with significant impacts. It sets the process by which they are studied, modified and entitled. Data centers' energy load, water-cooled infrastructure and industrial footprints touch nearly every environmental category the law was written to examine.
For underwriters, the key provision is anti-segmentation, which requires the whole project and future phases to be analyzed if any part needs a discretionary approval. Most California data center projects trigger at least one such approval, typically a conditional use permit, design review or zoning change. A first-phase approval therefore sets entitlement risk for later phases on a phased campus, and diligence should establish which approvals the first phase pulls in.
A site can avoid the statute only if its approvals are ministerial or fully by right. Brady writes that such sites are rare. They are most likely on industrially zoned land with older codes that permit industrial uses broadly, and they are difficult to find.
His prescription is to build CEQA into site strategy from the outset rather than treat it as a compliance step near the finish. He applies it to smaller facilities and to location-sensitive infrastructure that must be built in California to serve the market, not only to large campuses.
Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections