At a glance
- Capacity commitment charges under the agreement "are based on a rate of approximately $1.5 million per MW of requested capacity above 5 MW," the filing said.
- For a developer or fund underwriting a compute project in TVA's territory, a 100 MW request would carry about $142 million in capacity commitment charges at the filed rate.
- The tariff phases in through 2029, the Nashville Scene reported in August.
TVA expects $1.7 billion in aggregate payments from an unnamed data center customer under the large-load tariff it put into effect Oct. 1, the federal utility said in a Nov. 12 SEC filing. Capacity commitment charges under the agreement "are based on a rate of approximately $1.5 million per MW of requested capacity above 5 MW," the filing said. If the whole $1.7 billion were priced at that rate, it would correspond to roughly 1,130 MW of requested capacity above the 5 MW threshold.
For a developer or fund underwriting a compute project in TVA's territory, a 100 MW request would carry about $142 million in capacity commitment charges at the filed rate. That charge applies to the 95 MW above the 5 MW threshold.
The tariff phases in through 2029, the Nashville Scene reported in August. Existing customers keep their existing rate structure for part of that period. The $1.5 million rate reflects TVA's current cohort-based pricing methodology, which the filing said may be revised for future customer cohorts, so identical megawatts can carry different costs depending on when the contract was signed.
CEO Mike Skaggs told analysts on a Nov. 13 earnings call that the change to data center rates has supported the utility's investments. Those include extending the lives of TVA's existing nuclear units and expanding the nuclear fuel and supply hub in East Tennessee, he said. CFO Tom Rice said on the call that TVA is in a "strong financial position" to carry out a $13 billion capital plan over the next three years, on top of more than $23 billion invested since 2020.
The same rate produces a $142M and a $1.7B bill
Capacity commitment charges at about $1.5M per MW of requested capacity above 5 MW
100 MW request
$142M
- Capacity above 5 MW
- 95 MW
- Rate per MW
- $1.5M
Disclosed deal
$1.7B
- Implied capacity above 5 MW
- ~1,130 MW
- Customer
- Unnamed data center
Show as table
| 100 MW request | Disclosed deal | |
|---|---|---|
| Figure | $142M | $1.7B |
| Capacity above 5 MW | 95 MW | |
| Rate per MW | $1.5M | |
| Implied capacity above 5 MW | ~1,130 MW | |
| Customer | Unnamed data center |
Reported by the Energy Transition desk from Utility Dive, TVA SEC filing, Nov. 12, 2026 and Nashville Scene. Published . Corrections