At a glance
- The Texas Commission on Environmental Quality acted after the governor's office gave notice on Nov. 13, ending a pause that outgoing Gov.
- For anyone underwriting Texas compute, the permit queue is open again, but ERCOT's December report and a promised moratorium leave the rules unsettled.
- ERCOT said it received responses from 93% of 465 projects, which it called enough data for a meaningful analysis of the community impacts of data centers, according to Data Center Dynamics.
Texas's environmental regulator resumed reviewing data center permits on Nov. 16 and immediately issued a major air permit for SpaceX's planned $24 billion gas-fired data center east of Brownsville.
The Texas Commission on Environmental Quality acted after the governor's office gave notice on Nov. 13, ending a pause that outgoing Gov. Greg Abbott imposed in August. "The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement to the Texas Tribune.
For anyone underwriting Texas compute, the permit queue is open again, but ERCOT's December report and a promised moratorium leave the rules unsettled. Gov.-elect Gena Hinojosa, who defeated Abbott, campaigned on a pledge to pause new data center development until legislators pass clearer rules, and she takes office in January 2027.
ERCOT said it received responses from 93% of 465 projects, which it called enough data for a meaningful analysis of the community impacts of data centers, according to Data Center Dynamics. The information, gathered with the Public Utility Commission of Texas, covers how far data centers pay their own way, whether they supply their own power or draw it from the grid, whether they bring or reuse their own water, what they do to limit effects on neighboring property owners, and who owns and controls each project. ERCOT expects to file a formal report with regulators in December.
The permit TCEQ issued is a major air pollution permit for a gas-fired power plant and supercomputing facility on a 444-acre tract at Starbase City, east of Brownsville. The project was disclosed earlier this month, as Private Infrastructure Daily previously reported. Cameron County commissioners voted earlier this week against the company's request for a tax break for the facility.
ERCOT is weighing more than 474 GW of connection requests, more than five times the state's record peak electricity demand.
Permits reopened before the rules are written
Dated steps in Texas data center permitting, Aug. 2026-Jan. 2027
- Aug 2026Abbott pauses data center permits (Completed)
- Nov 13, 2026Governor's office gives notice to TCEQ (Completed)
- Nov 16, 2026TCEQ resumes reviews and issues SpaceX air permit (Current stage)
- Dec 2026ERCOT report due to regulators (Upcoming)
- Jan 2027Gov.-elect Hinojosa, who pledged a pause, takes office (Upcoming)
Show as table
| Date | Event | Detail |
|---|---|---|
| Aug 2026 | Abbott pauses data center permits | |
| Nov 13, 2026 | Governor's office gives notice to TCEQ | |
| Nov 16, 2026 | TCEQ resumes reviews and issues SpaceX air permit | |
| Dec 2026 | ERCOT report due to regulators | |
| Jan 2027 | Gov.-elect Hinojosa, who pledged a pause, takes office |
The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations.Laura Lopez, TCEQ spokesperson
Reported by the Data centers & fiber desk from Data Center Dynamics, Texas Tribune and Private Infrastructure Daily archive. Published . Corrections