TCEQ resumes data center permits and issues SpaceX air permit

The regulator lifted an August pause and issued a permit for SpaceX's $24 billion gas-fired data center east of Brownsville.

At a glance

  1. The Texas Commission on Environmental Quality acted after the governor's office gave notice on Nov. 13, ending a pause that outgoing Gov.
  2. For anyone underwriting Texas compute, the permit queue is open again, but ERCOT's December report and a promised moratorium leave the rules unsettled.
  3. ERCOT said it received responses from 93% of 465 projects, which it called enough data for a meaningful analysis of the community impacts of data centers, according to Data Center Dynamics.

Texas's environmental regulator resumed reviewing data center permits on Nov. 16 and immediately issued a major air permit for SpaceX's planned $24 billion gas-fired data center east of Brownsville.

The Texas Commission on Environmental Quality acted after the governor's office gave notice on Nov. 13, ending a pause that outgoing Gov. Greg Abbott imposed in August. "The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement to the Texas Tribune.

For anyone underwriting Texas compute, the permit queue is open again, but ERCOT's December report and a promised moratorium leave the rules unsettled. Gov.-elect Gena Hinojosa, who defeated Abbott, campaigned on a pledge to pause new data center development until legislators pass clearer rules, and she takes office in January 2027.

ERCOT said it received responses from 93% of 465 projects, which it called enough data for a meaningful analysis of the community impacts of data centers, according to Data Center Dynamics. The information, gathered with the Public Utility Commission of Texas, covers how far data centers pay their own way, whether they supply their own power or draw it from the grid, whether they bring or reuse their own water, what they do to limit effects on neighboring property owners, and who owns and controls each project. ERCOT expects to file a formal report with regulators in December.

The permit TCEQ issued is a major air pollution permit for a gas-fired power plant and supercomputing facility on a 444-acre tract at Starbase City, east of Brownsville. The project was disclosed earlier this month, as Private Infrastructure Daily previously reported. Cameron County commissioners voted earlier this week against the company's request for a tax break for the facility.

ERCOT is weighing more than 474 GW of connection requests, more than five times the state's record peak electricity demand.

Permits reopened before the rules are written

Dated steps in Texas data center permitting, Aug. 2026-Jan. 2027

  1. Aug 2026Abbott pauses data center permits (Completed)
  2. Nov 13, 2026Governor's office gives notice to TCEQ (Completed)
  3. Nov 16, 2026TCEQ resumes reviews and issues SpaceX air permit (Current stage)
  4. Dec 2026ERCOT report due to regulators (Upcoming)
  5. Jan 2027Gov.-elect Hinojosa, who pledged a pause, takes office (Upcoming)
Source: TCEQ, ERCOT and governor's office via Data Center Dynamics
Show as table
DateEventDetail
Aug 2026Abbott pauses data center permits
Nov 13, 2026Governor's office gives notice to TCEQ
Nov 16, 2026TCEQ resumes reviews and issues SpaceX air permit
Dec 2026ERCOT report due to regulators
Jan 2027Gov.-elect Hinojosa, who pledged a pause, takes office
The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations.Laura Lopez, TCEQ spokesperson

Reported by the Data centers & fiber desk from Data Center Dynamics, Texas Tribune and Private Infrastructure Daily archive. Published . Corrections

Related

Infrastructure

Abbott freezes Texas data center permits, making grid access a state grant

The audit's ownership question turns a permit into a disclosure document, and 49.8GW of Texas projects now wait on a December deadline.

Infrastructure

DataBank CEO says Texas grid pause won't alter its buildout

Raul Martynek says the audit of large-load connections is manageable, with 470GW of requests queued at ERCOT.

Infrastructure

Data center contractors say new state rules extend permitting without cooling demand

Virginia, Pennsylvania and Texas have each constrained data center permitting since August, and builders describe the friction as entitlement risk rather than a thinning order book.

Infrastructure

Orange seeks partners for 24-pair ReuNION leg to Singapore

Phase one to South Africa, carrying 320 Tbps across 16 fiber pairs, has a provisional launch expected in early 2029.

Infrastructure

CEQA can add years to California data center schedules

DLA Piper partner Andrew Brady writes that the law's anti-segmentation rule ties later phases to the first discretionary approval.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

TCEQ resumes data center permits and issues SpaceX air permit