SWI launches AI cloud unit with 3.6GW of power

The unit will start with 30MW in Cambridge and targets 2.3GW of Nvidia-focused capacity by 2029.

At a glance

  1. Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported.
  2. The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.
  3. SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.

SWI Group on Monday launched SWI Compute, an AI cloud unit supported by 3.6GW of power capacity across 24 sites in the US and Europe, starting with 30MW at a planned Cambridge, UK, campus.

Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported. The first 30MW is expected online by the end of 2027 and is the initial phase of a UK campus planned to reach 530MW. SWI is targeting 2.3GW of Nvidia-focused capacity by 2029.

The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.

SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.

SWI Group, listed on Euronext Amsterdam, reports €11 billion ($12.27 billion) in assets under management, so the approximately $1 billion hardware order is equivalent to about 8% of AUM. Halil Mirakhmedov, CEO of SWI Compute, said the team secured those advanced Nvidia hardware orders after joining the Nvidia Cloud Partner program, and that SWI Group had spent six years acquiring grid access.

SWI Group was formed from the merger of Stoneweg and Icona Capital last year. It took a stake in AiOnX, which has data center projects in the UK, Ireland and mainland Europe, and said every SWI Compute site will be built to Nvidia reference architectures and DSX AI Factory Platform requirements.

SWI Compute's power ladder: 30MW at launch against 3.6GW secured

The first Cambridge phase is 5.7% of the planned campus

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity target, 20292.3K MW
  • Cambridge campus, planned530 MW
  • First Cambridge phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
First Cambridge phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity target, 20292.3K MW
Power secured group-wide, 24 sites3.6K MW

SWI Compute's power ladder: a 30MW start against 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: a 30MW start against 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · company figures
Show as table
ItemValue (MW)
Power secured group-wide, 24 sites3.6K MW
Nvidia-focused capacity, 2029 target2.3K MW
Cambridge campus, planned530 MW
Cambridge first phase, end-202730 MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Group power secured, 24 sites3.6K MW
Nvidia-focused capacity, 2029 target2.3K MW
Cambridge campus, planned530 MW
Cambridge first phase, end-202730 MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Group power secured, 24 sites3.6K MW
Nvidia-focused capacity, 2029 target2.3K MW
Cambridge campus, planned530 MW
Cambridge first phase, end-202730 MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Power secured group-wide, 24 sites3.6K MW
Nvidia-focused capacity, 2029 target2.3K MW
Cambridge campus, planned530 MW
Cambridge first phase, end-202730 MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity target (2029)2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase (end-2027)30 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase (end-2027)30 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity target (2029)2.3K MW
Power secured group-wide, 24 sites3.6K MW

SWI Compute's power ladder: a 30MW start against 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity target (2029)2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase (end-2027)30 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase (end-2027)30 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity target (2029)2.3K MW
Power secured group-wide, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW

The first Cambridge phase is a sliver of what is planned and already secured

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused target, 20292.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Power secured group-wide, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · company figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · company figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · company figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power plans: 30MW first phase up to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute
Show as table
ItemValue (MW)
Group power secured, 24 sites3.6K MW
Nvidia-focused capacity, 2029 target2.3K MW
Cambridge campus, planned530 MW
Cambridge first phase, end-202730 MW

SWI Compute's power build-out: 30MW first phase, 3.6GW secured

The first Cambridge phase is a fraction of what is planned and already secured

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · SWI Compute figures
Show as table
LabelValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power build-out: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of the planned campus and the 2029 target

  • Group power secured, 24 sites3.6K MW
  • Nvidia-focused capacity, 2029 target2.3K MW
  • Cambridge campus, planned530 MW
  • Cambridge first phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · SWI Compute figures
Show as table
LabelValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what's planned and already secured

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 20293.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power build-out: 30MW first phase to 3.6GW secured

The first Cambridge phase is a sliver of what is planned and already secured

30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase, end-2027530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder, 30MW to 2.3GW

The first Cambridge phase is a sliver of what the company plans to build

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused capacity, 2029 target30 MWCambridge first phase530 MW2.3K MWNvidia-focused capacity, 2029 target30 MWCambridge first phase530 MW2.3K MWNvidia-focused capacity, 2029 target
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity, 2029 target2.3K MW

SWI Compute's power ladder, from 30MW to 3.6GW

The first Cambridge phase is a sliver of what's planned and secured

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 20293.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power build-out, from 30MW to 3.6GW

The first Cambridge phase is a sliver of what's planned and secured

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 20293.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power build-out: 30MW now to 3.6GW secured

The first Cambridge phase is a sliver of what's planned

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 20293.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder, in MW

The first Cambridge phase is a sliver of what's planned

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 20293.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites30 MWCambridge first phase530 MW2.3K MW3.6K MWGroup power secured, 24 sites
Source: Data Center Dynamics · company figures
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW
Group power secured, 24 sites3.6K MW

SWI Compute's power ladder, in MW

The first Cambridge phase is a sliver of what's planned

30 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 202930 MWCambridge first phase530 MWCambridge campus, planned2.3K MWNvidia-focused target, 202930 MWCambridge first phase530 MW2.3K MWNvidia-focused target, 2029
Source: Data Center Dynamics
Show as table
LabelValue (MW)
Cambridge first phase30 MW
Cambridge campus, planned530 MW
Nvidia-focused target, 20292.3K MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

SWI raises €800 million in equity for US and Europe data center buildout

The Euronext Amsterdam-listed investor says total equity raised since March 2026 now exceeds €1 billion ($1.1bn).

Infrastructure

Cadence launches Munich AI data center with Nvidia chips

The site hosts OnCloud, Reality Digital Twin and the Millennium M2000; OnCloud is available to European customers now.

Infrastructure

Forum Edge signs $94.4M Nvidia B300 reservation with Fireworks

The 36-month Dallas capacity deal is the joint venture's first contracted customer commitment.

Infrastructure

G42 signs Greece AI factory MoUs with Copelouzos and Khazna

Khazna would build the data centers and Core42 would supply cloud and AI compute; no project details were shared.

Infrastructure

Verizon signs AWS AI infrastructure deal worth more than $2 billion

The AWS agreement follows a $1 billion dark fiber deal with Google; Verizon puts all signed contracts at about $4 billion.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections