At a glance
- Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported.
- The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.
- SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.
SWI Group on Monday launched SWI Compute, an AI cloud unit supported by 3.6GW of power capacity across 24 sites in the US and Europe, starting with 30MW at a planned Cambridge, UK, campus.
Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported. The first 30MW is expected online by the end of 2027 and is the initial phase of a UK campus planned to reach 530MW. SWI is targeting 2.3GW of Nvidia-focused capacity by 2029.
The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.
SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.
SWI Group, listed on Euronext Amsterdam, reports €11 billion ($12.27 billion) in assets under management, so the approximately $1 billion hardware order is equivalent to about 8% of AUM. Halil Mirakhmedov, CEO of SWI Compute, said the team secured those advanced Nvidia hardware orders after joining the Nvidia Cloud Partner program, and that SWI Group had spent six years acquiring grid access.
SWI Group was formed from the merger of Stoneweg and Icona Capital last year. It took a stake in AiOnX, which has data center projects in the UK, Ireland and mainland Europe, and said every SWI Compute site will be built to Nvidia reference architectures and DSX AI Factory Platform requirements.
SWI Compute's power ladder: 30MW at launch against 3.6GW secured
The first Cambridge phase is 5.7% of the planned campus
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused capacity target, 20292.3K MW
- Cambridge campus, planned530 MW
- First Cambridge phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| First Cambridge phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity target, 2029 | 2.3K MW |
| Power secured group-wide, 24 sites | 3.6K MW |
SWI Compute's power ladder: a 30MW start against 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: a 30MW start against 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Power secured group-wide, 24 sites | 3.6K MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Cambridge campus, planned | 530 MW |
| Cambridge first phase, end-2027 | 30 MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Group power secured, 24 sites | 3.6K MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Cambridge campus, planned | 530 MW |
| Cambridge first phase, end-2027 | 30 MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Group power secured, 24 sites | 3.6K MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Cambridge campus, planned | 530 MW |
| Cambridge first phase, end-2027 | 30 MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Power secured group-wide, 24 sites | 3.6K MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Cambridge campus, planned | 530 MW |
| Cambridge first phase, end-2027 | 30 MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused capacity target (2029)2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase (end-2027)30 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase (end-2027) | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity target (2029) | 2.3K MW |
| Power secured group-wide, 24 sites | 3.6K MW |
SWI Compute's power ladder: a 30MW start against 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused capacity target (2029)2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase (end-2027)30 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase (end-2027) | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity target (2029) | 2.3K MW |
| Power secured group-wide, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW
The first Cambridge phase is a sliver of what is planned and already secured
- Power secured group-wide, 24 sites3.6K MW
- Nvidia-focused target, 20292.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Power secured group-wide, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power plans: 30MW first phase up to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Group power secured, 24 sites | 3.6K MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Cambridge campus, planned | 530 MW |
| Cambridge first phase, end-2027 | 30 MW |
SWI Compute's power build-out: 30MW first phase, 3.6GW secured
The first Cambridge phase is a fraction of what is planned and already secured
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power build-out: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of the planned campus and the 2029 target
- Group power secured, 24 sites3.6K MW
- Nvidia-focused capacity, 2029 target2.3K MW
- Cambridge campus, planned530 MW
- Cambridge first phase, end-202730 MW
Show as table
| Item | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what's planned and already secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power build-out: 30MW first phase to 3.6GW secured
The first Cambridge phase is a sliver of what is planned and already secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase, end-2027 | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder, 30MW to 2.3GW
The first Cambridge phase is a sliver of what the company plans to build
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused capacity, 2029 target | 2.3K MW |
SWI Compute's power ladder, from 30MW to 3.6GW
The first Cambridge phase is a sliver of what's planned and secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power build-out, from 30MW to 3.6GW
The first Cambridge phase is a sliver of what's planned and secured
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power build-out: 30MW now to 3.6GW secured
The first Cambridge phase is a sliver of what's planned
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder, in MW
The first Cambridge phase is a sliver of what's planned
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
| Group power secured, 24 sites | 3.6K MW |
SWI Compute's power ladder, in MW
The first Cambridge phase is a sliver of what's planned
Show as table
| Label | Value (MW) |
|---|---|
| Cambridge first phase | 30 MW |
| Cambridge campus, planned | 530 MW |
| Nvidia-focused target, 2029 | 2.3K MW |
Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections