Stack Infrastructure affiliate files for second Lancaster data center building

The DFW02B filing carries a $540 million construction budget and a March 2027 to December 2028 schedule.

At a glance

  1. The two-story building would sit at 1130 E. Belt Line Road in Dallas County.
  2. Stack's sales brochure assigns 54MW to the building and describes DFW02 as a 500MW campus on 193 acres in South Dallas that could reach five buildings, 1.76 million sq ft and an on-site substation.
  3. Stack's latest filing follows DFW02A at 1000 E Belt Line Road, a 360,030 sq ft, two-story building due for completion in March 2027.

Stack Infrastructure's affiliate SI DFW02CAMPUS LLC filed this month for DFW02B, a 350,045 sq ft data center and office building in Lancaster, Data Center Dynamics reported. The two-story building would sit at 1130 E. Belt Line Road in Dallas County.

The Texas Department of Licensing and Regulation application sets a $540 million construction budget and a March 2027 to December 2028 schedule. Stack's sales brochure assigns 54MW to the building and describes DFW02 as a 500MW campus on 193 acres in South Dallas that could reach five buildings, 1.76 million sq ft and an on-site substation.

Stack's latest filing follows DFW02A at 1000 E Belt Line Road, a 360,030 sq ft, two-story building due for completion in March 2027. DFW02A was filed in January 2025, with follow-up works running to March 2028. DFW02B's construction start therefore lands in the same month DFW02A is scheduled to finish, per those filings.

The $540 million budget and 54MW figure work out to roughly $10 million per megawatt, if they cover the same scope. The filing does not break the budget down that way, and it is a per-building figure, not a campus one, because the other four buildings have no disclosed cost.

BuildingAddressSizePowerConstruction window
DFW02A1000 E Belt Line Road, Lancaster360,030 sq ftNot disclosedCompletion March 2027; follow-up works to March 2028
DFW02B1130 E Belt Line Road, Lancaster350,045 sq ft54MW (brochure)March 2027 to December 2028; $540 million

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Skybox and Prologis file for fourth and largest Hutto data center

The 846,300 sq ft single-story building would be the biggest at the PowerCampus site, with construction set for January 2027 and $550 million from Skybox.

Infrastructure

3 G Investments files application for 3.34m sq ft Augusta data center campus

The proposed Nixon Technology Center would occupy 388 acres near Augusta Regional Airport, with no data center developer or end user named in the report.

Infrastructure

Soluna files for 112MW Kati II data center in Willacy, Texas

The Texas filing estimates $471.8 million for a single 471,884 sq ft building and gives no construction timeline.

Infrastructure

Switzerland publishes up to CHF 7bn government cloud tender

Two public-cloud tiers cap at CHF 2 billion each and the private lot at CHF 3 billion; awards due summer 2027.

Infrastructure

gFiber to take over Ting's Colorado Springs dark fiber lease

Terms were not disclosed; Ting will keep serving Colorado Springs customers until the transition completes, no later than June 30, 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections