Riot signs $28 billion AI lease for Texas data center

The 15-year triple-net deal covers the full Corsicana campus, with the first 400MW due in September 2027.

$28BValue of Riot's Corsicana lease contract

At a glance

  1. Riot values the contract at $28 billion, rising to $54 billion if both five-year extension options are exercised.
  2. The 910MW will be delivered in three phases: 400MW in September 2027, 200MW in January 2028 and the final 310MW in July 2028.
  3. For investors underwriting Riot, the unnamed tenant leaves the $28 billion of contracted payments without an identified counterparty.

Riot Platforms signed a 15-year triple-net lease for 910MW of IT capacity with an unnamed AI lab at its Corsicana, Texas, data center, according to Data Center Dynamics.

Riot values the contract at $28 billion, rising to $54 billion if both five-year extension options are exercised.

The 910MW will be delivered in three phases: 400MW in September 2027, 200MW in January 2028 and the final 310MW in July 2028. The lease covers the whole Corsicana campus in Navarro County, about 50 miles southeast of Dallas.

For investors underwriting Riot, the unnamed tenant leaves the $28 billion of contracted payments without an identified counterparty. Jason Les, chief executive, said: "With total capital costs of approximately $6 million per IT megawatt, the Corsicana development will require about half the capital of a Tier 3 build." Across 910MW that implies roughly $5.5 billion of construction spending against $28 billion of contracted revenue over the initial term, or about $2 million per megawatt a year.

Riot said the Corsicana lease and its Rockdale contracts together total 1.1GW and about $38 billion of data center revenue. Les expects that portfolio to generate more than $2 billion of average annual net operating income at full deployment. He said the lower build cost and Riot's balance sheet mean "we do not currently anticipate issuing equity to fund our announced projects."

Les said Riot signed the Rockdale lease with the same lab earlier this year. AMD also leases 50MW at Rockdale, and Anthropic recently signed for 191MW there. Riot, formerly Riot Blockchain, was one of the world's largest bitcoin miners and has been shifting toward AI and HPC data centers since 2024.

Two-thirds of Corsicana's capacity arrives by early 2028

IT capacity delivered per phase, MW, Sept. 2027-Jul. 2028

400 MWSep 2027200 MWJan 2028310 MWJul 2028400 MWSep 2027200 MWJan 2028310 MWJul 2028400 MWSep 2027200 MWJan 2028310 MWJul 2028
Source: Data Center Dynamics
Show as table
LabelValue (MW)
Sep 2027400 MW
Jan 2028200 MW
Jul 2028310 MW
With total capital costs of approximately $6 million per IT megawatt, the Corsicana development will require about half the capital of a Tier 3 buildJason Les, chief executive of Riot Platforms

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Anthropic discloses $895.4bn in compute and data center commitments

Google, SpaceX, Amazon and Microsoft account for $396.7 billion of the total, and three of those four contracts are payable regardless of usage.

Infrastructure

Fluor wins EPC contract for TeraWulf's $4 billion Kentucky campus

The definitive award covers three buildings at the Justified Data Campus, with ready-for-service completions phased from late 2027 into mid-2028.

Infrastructure

Anthropic takes over $3.4bn Caterpillar generator order for 1.7GW

Texas supplier OnePWR will help install the 1.7GW of generators at Anthropic sites, with sets expected within two years.

Infrastructure

AirTrunk named operator of proposed 935,730 sqm Melbourne campus

The site would sit on 67 hectares in McMullin's Fusion Business Park, with community sessions set for November.

Infrastructure

Nvidia pitches Apollo on up to 1GW of edge compute at Brightspeed

The Information reports the two are sharing information and arranging potential site visits, with first capacity possibly live as soon as Q1 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

Riot signs $28 billion AI lease for Texas data center