AirTrunk named operator of proposed 935,730 sqm Melbourne campus

The site would sit on 67 hectares in McMullin's Fusion Business Park, with community sessions set for November.

At a glance

  1. The site sits inside the 67-hectare Fusion Business Park, owned by real estate firm McMullin, and is close to the Kalkallo Zone Substation.
  2. The project would be built across up to seven buildings.
  3. Nearby households would be able to receive an AU$200 (US$137.88) annual deduction on a standard electricity bill via Origin Energy.

AirTrunk said this week it is the operator behind a proposed 935,730 sqm data center campus at 45 Donnybrook Road in Mickleham, about 35km north of central Melbourne. The site sits inside the 67-hectare Fusion Business Park, owned by real estate firm McMullin, and is close to the Kalkallo Zone Substation.

The project would be built across up to seven buildings. AirTrunk said the campus would use air-based cooling and would not draw community water during normal operations. The developer would fund its own grid connection and deliver new renewable energy projects.

Nearby households would be able to receive an AU$200 (US$137.88) annual deduction on a standard electricity bill via Origin Energy.

For allocators underwriting Australian data center assets, the pledges put the grid connection and the household electricity deduction on the operator's books, not on the network or residents.

Blackstone and the Canadian Pension Plan acquired AirTrunk in 2024 for US$16.1 billion. AirTrunk, founded in 2018, already has two Melbourne campuses. The Mickleham project would be its third. Community information sessions are scheduled for November.

Mickleham lifts Melbourne level with Sydney

AirTrunk campuses operating or under development by city, including the proposed Mickleham site

  • Sydney3 campuses
  • Melbourne3 campuses
  • Tokyo2 campuses
  • Osaka2 campuses
  • Singapore1 campuses
  • Hong Kong1 campuses
  • Johor1 campuses
Source: AirTrunk via Data Center Dynamics
Show as table
ItemValue (campuses)
Sydney3 campuses
Melbourne3 campuses
Tokyo2 campuses
Osaka2 campuses
Singapore1 campuses
Hong Kong1 campuses
Johor1 campuses

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

AirTrunk raises A$4.25bn green loan for Sydney campus

Thirty-two lenders backed the SYD3 facility, bringing AirTrunk's committed debt to about A$38.4bn; the expansion is due for completion in mid-2028.

Infrastructure

AirTrunk plans to push its IPO to 2027, citing rates and volatility

The Blackstone-backed firm had planned to list this year, raise $1.5 billion and gauge investor interest this month.

Infrastructure

Anthropic's data center arm hires the architect of Equinix's hyperscale JVs

Theseus puts the anchor tenant on the cap table, which solves the lease and double-stacks the credit on one demand forecast.

Infrastructure

Riot signs $28 billion AI lease for Texas data center

The 15-year triple-net deal covers the full Corsicana campus, with the first 400MW due in September 2027.

Infrastructure

Fluor wins EPC contract for TeraWulf's $4 billion Kentucky campus

The definitive award covers three buildings at the Justified Data Campus, with ready-for-service completions phased from late 2027 into mid-2028.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections