Poland's three-site national data center wins PLN 1.56bn EU grant

The Ministry of Digital Affairs and NASK-PIB project is now slated for 2029 completion, after a cancelled procurement round and a first-phase cost ceiling of PLN 1.6bn.

At a glance

  1. The grant pays for three data centers in separate parts of the country, each roughly 2,000 square meters, or 21,500 square feet, and built to the EN 50600 standard, the European benchmark for facility design.
  2. At 21,500 square feet apiece, the halls are small by commercial standards, suggesting capacity for government workloads rather than paying tenants.
  3. The schedule has slipped from a 2024–2026 construction window to a 2029 completion estimate after an earlier procurement round was cancelled, and the budget moved with it: CRN puts the first-phase cost ceiling at PLN 1.6 billion, about $411 million, this year, up from PLN 1 billion, then $280 million, in 2025.

Poland has drawn PLN 1.56 billion, about $401 million, from the European Union's European Funds for Digital Development program to build its National Data Processing Center, a government project overseen by the Ministry of Digital Affairs and the Scientific and Academic Computer Network – National Research Institute, or NASK-PIB.

The grant pays for three data centers in separate parts of the country, each roughly 2,000 square meters, or 21,500 square feet, and built to the EN 50600 standard, the European benchmark for facility design. A fiber-optic network will connect the three so they can communicate independently of one another, a redundancy design in which the failure of one hall does not take the government's systems down with it, and the award also covers related IT infrastructure. Conceived in 2022, the system was framed as a way to strengthen the cybersecurity resilience of the Polish government.

At 21,500 square feet apiece, the halls are small by commercial standards, suggesting capacity for government workloads rather than paying tenants.

The schedule has slipped from a 2024–2026 construction window to a 2029 completion estimate after an earlier procurement round was cancelled, and the budget moved with it: CRN puts the first-phase cost ceiling at PLN 1.6 billion, about $411 million, this year, up from PLN 1 billion, then $280 million, in 2025. Against that ceiling, the PLN 1.56 billion grant covers nearly all of the first phase.

The project has now spent four years between first announcement and funded start: floated in 2022, planned for 2024 to 2026, reset this year to 2029. It carries the shape of a public build in which the money arrives after the plan and construction follows the money. For the government systems the halls are meant to protect, that leaves the resilience promised in 2022 still several years out.

A second, smaller award runs alongside it: PLN 172.7 million, $44.3 million, from the same program for the ministry's Government Cloud Computing project, called RCho, which will expand cloud infrastructure, add applications and IT solutions, and prepare the platform for integration with future AI services. The ministry issued a call for proposals to expand RCho in April, and the confirmation of both grants arrived later, funding a plan the ministry had already sketched: halls for the data and a cloud platform for the services on top of it.

Grant covers 97.5% of the PLN 1.6bn first phase

Poland's National Data Processing Center and RCho cloud, PLN bn

  • First-phase cost ceiling1.6 PLN bn
  • National data centers (EU grant)1.56 PLN bn
  • Government cloud RCho (EU grant)0.17 PLN bn
Source: European Funds for Digital Development / CRN via Data Center Dynamics · 2026
Show as table
ItemValue (PLN bn)
First-phase cost ceiling1.6 PLN bn
National data centers (EU grant)1.56 PLN bn
Government cloud RCho (EU grant)0.17 PLN bn

A sovereign tenant against a merchant pipeline

The two grants are small against the market being built around them: Poland has drawn several major data center developments in the past year, and a PwC report with analysis by xyz.pl puts cumulative investment in the sector at up to PLN 292.90 billion, or $75.3 billion, between 2027 and 2036, a pipeline shaped by commercial and hyperscale capacity rather than government halls. The National Data Processing Center is a different sort of asset: state compute for state functions, paid from a state-and-EU balance sheet rather than a lease.

That difference shapes how the asset is valued. As this publication has argued, a digital-infrastructure asset earns infrastructure pricing when it carries a named anchor tenant or a sovereign buyer; without one, it is a merchant shell waiting for a counterparty. The Polish project skips the wait, because the sovereign is the buyer and the European program is the financing. The risk here is procurement and schedule, not vacancy: the cancelled round that pushed a 2026 target to 2029, and a cost ceiling already revised upward once. Sovereign builds move on public clocks, through funding rounds and procurement cycles, rather than the lease-signing pace that governs a commercial hall.

The instinct to put public money into the physical layer shows up on the other side of the Atlantic, where Washington State's $1.9 billion SPARK package directs state dollars at grid capacity for the data center buildout, buying power on lines that already exist rather than new corridors. Poland's award differs in kind, since it funds the computing halls themselves, but it rests on the same premise: the state can stand in as the anchor.

A grant of PLN 1.56 billion for three government facilities, plus PLN 172.7 million for a cloud platform and its AI ambitions, is small next to the PLN 292.90 billion commercial forecast, but it gives other governments weighing where their own data should sit a working example of routing EU money into sovereign compute. The next dates to watch are the April call for RCho proposals and the 2029 completion estimate for the three halls, a schedule the project has already missed once.

The Polish project skips the wait, because the sovereign is the buyer and the European program is the financing.

Reported by the Data centers & fiber desk from Data Center Dynamics, CRN (as reported by Data Center Dynamics), PwC and xyz.pl. Published . Corrections

Related

RIAs

Sanctuary Wealth adds bQuest aging-care tools for partner firms

Advisors get a readiness assessment and care-coordination concierge; pricing was not included in the coverage.

Advisors

A WealthManagement.com column says hotel estate plans must transfer operating authority, not just ownership

The column breaks succession into three transfers: ownership, decision rights and operating authority.

Real Estate

Los Angeles County office leasing hits highest since 2019 on renewals

Savills reports about 4 million square feet leased in the third quarter as overall availability fell to 26.5 percent.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections