Skip to content
Friday, October 23, 2026 · Today’s edition, 6:30 a.m. ETFri, Oct 23 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Nscale's Glomfjord data center six months behind schedule as IPO nears

Only 6.4MW of the Norwegian site's planned 30MW is operational, according to a Bloomberg report relayed by Data Center Dynamics.

At a glance

  1. The report cites people close to the project and public records for the setbacks: construction delays, local regulations, cooling-system leaks and a transformer fire.
  2. Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion.
  3. Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft.

Nscale's Glomfjord data center in Norway is about six months behind schedule, with 6.4MW of a planned 30MW operational, according to a Bloomberg report relayed by Data Center Dynamics.

The report cites people close to the project and public records for the setbacks: construction delays, local regulations, cooling-system leaks and a transformer fire. Bloomberg also reports that Nscale towed in the Kalmar floating hotel to house construction workers nearby, a step aimed at speeding construction.

Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion. Its prospectus, published in September, lists five active data centers totaling 55MW, with 12 more in development, and includes construction delays, construction site accidents and permit delays among its risk factors.

Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft. Revenue for the six months to the end of June 2026 came to $140.6 million. The company says that figure is up 1,252 percent year over year. Losses were $1.02 billion, compared with $368.9 million in the same period of 2025.

Nscale's half-year loss dwarfed its revenue

Six months to end of June 2026, compared with the same period a year earlier

  • H1 2026 net loss$1K
  • H1 2025 net loss$368.9M
  • H1 2026 revenue$140.6M
Source: Company IPO prospectus via Data Center Dynamics
Show as table
ItemValue ($M)
H1 2026 net loss$1K
H1 2025 net loss$368.9M
H1 2026 revenue$140.6M

Reported by the Data centers & fiber desk from Data Center Dynamics and Bloomberg (cited within the DCD report). Published . Corrections

Related

Infrastructure

Nscale's $3bn US IPO puts a $51bn backlog to the test

The UK neocloud aims for a September listing with Goldman and JPMorgan, betting public investors will pay infrastructure prices for a $51bn contracted-revenue backlog while it funds a 10GW buildout.

Infrastructure

Nvidia in talks to invest in Firmus after neocloud scrapped its IPO

The Information reports talks, not an agreement; a several hundred million dollar ticket would be a fraction of the $2bn–$3bn private raise Bloomberg reported Firmus was seeking.

Infrastructure

Anthropic in talks for second $45bn Nscale lease at West Virginia campus

The reported 460MW contract would double Anthropic's committed capacity at Monarch to 920MW, alongside Microsoft's 1.35GW.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections