Nebius secures $3.5bn Citi facility at SOFR plus 2.75 points

The one-year facility funds data center and GPU purchases and can step up to a maximum spread of 3.50 points over Term SOFR.

$3.5BNebius senior secured facility with Citi

Follow this story

Citi · Volt · Nebius · Ophir Nave · Neom · AIB Data Centers

At a glance

  1. Citi was mandated lead arranger, agent and security agent.
  2. For allocators who hold or underwrite GPU-cloud credit, the one-year maturity sets the next repricing point: the loan comes due in twelve months and any refinancing will be priced against the same Term SOFR benchmark.
  3. The $3.5 billion facility follows $5.75 billion of senior notes Nebius raised in August, which Private Infrastructure Daily described as carrying a four-point coupon spread.

Nebius said it secured a $3.5 billion senior secured facility from Citi, priced at 2.75 points over Term SOFR initially and maturing in one year.

The spread can rise to a maximum of 3.50 points over Term SOFR. Citi was mandated lead arranger, agent and security agent. Nebius will use the financing for data center development and GPU procurement, Data Center Dynamics reported Oct. 23.

For allocators who hold or underwrite GPU-cloud credit, the one-year maturity sets the next repricing point: the loan comes due in twelve months and any refinancing will be priced against the same Term SOFR benchmark. Nebius's chief operating officer, Ophir Nave, said the company retains a "range of capital sources" for the next phase, including asset-backed financing based on more than $40 billion of investment-grade customer commitments.

The secured line prices inside August's notes

The $3.5 billion facility follows $5.75 billion of senior notes Nebius raised in August, which Private Infrastructure Daily described as carrying a four-point coupon spread. The bank line is secured and matures in one year; the notes are longer-dated, so the 1.25-point gap between opening spreads is not a like-for-like credit comparison.

In October, Nebius signed data center leases with AIB Data Centers, Volt in the Netherlands and Neom's Oxagon. The AIB deal covers 50MW over 12 years, and the Oxagon agreement makes Nebius an anchor customer for up to 50MW, with capacity due online in phases from the fourth quarter of 2027, Data Center Dynamics reported.

Reported by the Fundraising desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Nebius takes up to 50MW as anchor customer at Neom's Oxagon

Humain and DataVolt signed the agreement on October 21, with capacity due online in phases from the fourth quarter of 2027.

Infrastructure

Nebius signs 50MW, 12-year capacity deal with AIB Data Centers

Tenant prepayments, along with project debt and equity, will fund two data halls at a site already carrying a 65MW electric service agreement.

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported $45 billion contract would double Anthropic's committed capacity at Monarch to 920MW; Microsoft already holds 1.35GW there.

Infrastructure

Vertical Semiconductor signs $73m CHIPS letter with Commerce stake

Up to $73 million supports US development and production of vertical GaN power transistors; Commerce gets a minority, non-voting equity stake.

Infrastructure

Sosteneo Fund II completes first external close above €150m

The Generali Investments unit says Fund II vintage commitments now exceed €450 million, with Fund I beginning distributions in the second quarter.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections