At a glance
- CEO Yukio Kani confirmed discussions with Amazon, Google and Microsoft, Data Center Dynamics reported.
- Jera, Dell and UK data center operator Rhaelm agreed in October to develop a 400MW behind-the-meter data center at the Chiba Thermal Power Station, with operations expected in 2028.
- For allocators, the key term is the standard design: Jera, Dell and Rhaelm agreed to standardize cooling systems, power supplies and other inputs so the model can be deployed across Jera's more than 20 thermal plants, which have an estimated combined capacity of almost 55GW.
Jera is in talks with Meta, Anthropic, Amazon, Google and Microsoft about building data centers at its thermal power plants near Tokyo, Nikkei first reported. CEO Yukio Kani confirmed discussions with Amazon, Google and Microsoft, Data Center Dynamics reported. Any agreements would likely follow the template set by an October deal at the Chiba Thermal Power Station.
Jera, Dell and UK data center operator Rhaelm agreed in October to develop a 400MW behind-the-meter data center at the Chiba Thermal Power Station, with operations expected in 2028. An estimated $15 billion is to be invested across all phases, including land, power infrastructure, construction and AI compute.
For allocators, the key term is the standard design: Jera, Dell and Rhaelm agreed to standardize cooling systems, power supplies and other inputs so the model can be deployed across Jera's more than 20 thermal plants, which have an estimated combined capacity of almost 55GW.
"We'll develop standard models capable of supporting a wide range of applications by clients and deploy them at multiple thermal power plants," Kani said.
The Chiba station is LNG-fired with a maximum output of 4.38GW, and the data center there would be the first colocated with a thermal asset in Japan, Nikkei reported. Nikkei named the Yokohama Thermal Power Station as another candidate. Jera signed a non-binding memorandum of understanding with the City of Yokohama in October to explore siting a data center there on low-carbon or decarbonized electricity.
One 400MW data center is small next to Jera's 55GW fleet
Power capacity in GW: Jera's thermal fleet, the Chiba plant, and the planned data center there
- Jera thermal fleet, 20+ plants55 GW
- Chiba Thermal Power Station4.38 GW
- Chiba data center (planned)0.4 GW
Show as table
| Item | Value (GW) |
|---|---|
| Jera thermal fleet, 20+ plants | 55 GW |
| Chiba Thermal Power Station | 4.38 GW |
| Chiba data center (planned) | 0.4 GW |
Reported by the Energy Transition desk from Data Center Dynamics, citing Nikkei. Published . Corrections