Entergy says Google deal would save Arkansas $500 million more

The amended contract would add 350 MW of storage and 440 MW of Pattern Energy solar, with Arkansas regulators set to hear it in January.

At a glance

  1. The amended service contract, filed with Arkansas regulators last month, would add 350 MW of battery storage at two sites if approved.
  2. For allocators who underwrite contracted generation and data-center load, the figure to test is how much of the new storage and solar bill the Google contract shifts off the remaining customer base.
  3. Google plans to spend $15 billion on Malaysian data centers through 2028, as Private Infrastructure Daily previously reported.

Entergy's amended application to serve Google's West Memphis data center would save Arkansas ratepayers at least $500 million more than the $1.6 billion previously agreed, CEO Drew Marsh told investors Monday on the company's third-quarter earnings call.

The amended service contract, filed with Arkansas regulators last month, would add 350 MW of battery storage at two sites if approved. Entergy would also procure 440 MW of solar from Pattern Energy's Big Island Solar project, the company said in a securities filing this week. The Arkansas Public Service Commission is set to hear the matter in January. The exact amount of additional power demand and other key details are redacted, the Arkansas Democrat-Gazette reported Oct. 20.

For allocators who underwrite contracted generation and data-center load, the figure to test is how much of the new storage and solar bill the Google contract shifts off the remaining customer base. Marsh's $500 million measures savings to the remaining customer base against the earlier version of the deal, which implies the amended contract assigns more of the new-build cost to Google. The January review is where that allocation gets tested, and it sets the revenue backing the two battery sites and the solar purchase.

Google plans to spend $15 billion on Malaysian data centers through 2028, as Private Infrastructure Daily previously reported.

The Arkansas contract is one of several capital items Entergy flagged for its four-state territory. In Mississippi, the utility asked state regulators last month for clearance to issue bonds offsetting approximately $237.8 million of costs from Winter Storm Fern, which Entergy said caused "severe damage" to its infrastructure. In Texas, the company said it has energized the Orange County Advanced Power Station, a 1,215-MW combined-cycle gas plant built to support load growth.

Louisiana regulators in October approved Entergy Louisiana's $1.2 billion, 500-kV Babel to Webre transmission project, Marsh said. LPSC staff also reached a settlement with the utility that Entergy said "resolves all outstanding issues" between the company, the commission staff and one intervenor in a proceeding over several gigawatts of generation and related infrastructure for Meta's planned Hyperion data center campus. The LPSC is set to vote on the matter next month.

Entergy's amended Google contract, by the numbers

Spending in $, capacity in MW, pending Arkansas approval

Extra ratepayer savings$500M
Battery storage added350 MW
Solar added440 MW
Babel to Webre project$1.2B
Source: Utility Dive, citing Entergy CEO Drew Marsh and a company securities filing

Reported by the Fundraising desk from Utility Dive and Private Infrastructure Daily archive (Google Malaysian data centers). Published . Corrections

Related

Infrastructure

Google backstops TeraWulf's 480MW Anthropic data center financing

The Justified campus in Kentucky is leased to Anthropic for 20 years under a $19 billion contract.

Infrastructure

Google plans $15 billion for Malaysian data centers through 2028

The investment funds campuses in Selangor and Negeri Sembilan plus 1GW of clean energy, on top of a $2 billion 2024 pledge.

Infrastructure

PSEG and Constellation plan 200-MW uprate at Salem

The uprate would support a recently announced nuclear power purchase agreement with Google, while Salem 1 stays offline for inspection.

Infrastructure

Bank of England asks about UK data center loans without tenants

The central bank is assessing how much risk banks carry in a sector where project costs have climbed.

Infrastructure

I Squared and AllianzGI close credit funds above target

I Squared's $3 billion was double its target, and AllianzGI's €1.5 billion beat its €1 billion goal by 50%.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections