At a glance
- The prepayments could finance up to 12.5% of the contracts Firmus is developing, the Australian Financial Review said.
- For advisors weighing neocloud exposure, the prepayment schedule determines how much of the 916MW contracted becomes cash before construction is finished.
- Prepayments are already part of the neocloud funding stack.
Firmus is seeking $3 billion in private equity and customer prepayments from Nvidia, OpenAI and Meta after shelving its IPO, the Australian Financial Review reported, citing three anonymous sources.
The prepayments could finance up to 12.5% of the contracts Firmus is developing, the Australian Financial Review said. As of September 2026, the Australian neocloud had 916MW of contracted capacity and 46MW running. Firmus blamed market volatility for the shelved listing.
For advisors weighing neocloud exposure, the prepayment schedule determines how much of the 916MW contracted becomes cash before construction is finished. The key diligence questions are which customers prepay, against what milestones, and whether the cash is tied to capacity already energised.
Prepayments are already part of the neocloud funding stack. Nebius said deals signed in its latest quarter carried prepayments covering 100% of the associated capex, as Private Wealth Daily previously reported. CoreWeave said more than 75% of its committed capex is tied to investment-grade and enterprise customers, with the remainder tied to AI labs and AI-native companies. The facilities can finance 70% to 100% of associated capex. Mike Intrator, CoreWeave's chief executive, said "recent volatility in the capital markets."
Firmus's 12.5% is a share of contracts in development, while CoreWeave's and Nebius's figures are shares of associated capex. Firmus's most recent private round raised $2bn at a $10.5bn post-money valuation. A $3bn equity raise would be half again the size of that round if the full amount is equity. Terms of the equity raise were not disclosed.
46MW runs against 916MW contracted
Capacity and fundraising figures for Firmus, as of Sept. 2026
Reported by the Data centers & fiber desk from Data Center Dynamics and Australian Financial Review (via Data Center Dynamics). Published . Corrections