At a glance
- The wider queue holds almost 600 projects representing nearly 125 GW across four study cycles, Utility Dive reported.
- For funds underwriting MISO solar and storage, the single-restudy limit is the change with lasting effect.
- The approved revisions let projects exit the queue without penalty before Decision Point II, which occurred Oct. 20.
FERC approved MISO's plan to clear its DPP-2022 interconnection queue, a study cycle of roughly 35 GW in active projects that the grid operator said would otherwise have run about 18 months late. The wider queue holds almost 600 projects representing nearly 125 GW across four study cycles, Utility Dive reported.
For funds underwriting MISO solar and storage, the single-restudy limit is the change with lasting effect. MISO will apply the cap to DPP-2022 and all future DPP cycles. Restudy counts set the study milestones developers use to time interconnection agreements and financial close, so a cap of one removes a recurring source of schedule slippage from the model.
The approved revisions let projects exit the queue without penalty before Decision Point II, which occurred Oct. 20. The 2022 cycle predates MISO's more recent interconnection reforms, and late withdrawals force restudies for every other project in the cycle. MISO proposed the changes on Sept. 21.
FERC also raised the penalty-free exit threshold to a 50% network upgrade cost increase from 35%. It rejected Ranger Power's argument that the penalty-free withdrawal terms reward unwanted behavior and are discriminatory.
The commission said the revisions "accomplish the purposes of the commission's final rules on generator interconnection" by helping ensure customers connect "in a reliable, efficient, transparent, and timely manner." The plan took effect Oct. 19, with some details outstanding pending decisions in two other dockets at the agency.
Reported by the Energy Transition desk from Utility Dive. Published . Corrections