Federal courts open colocation rebid with Washington in the requirements

The contract runs to 2029, but the RFI asks bidders to run the two data centers past 2032, gives Digital Realty and Csquare no automatic renewal, and prefers one site near Washington, D.C.

At a glance

  1. Today the split runs along the Mississippi River: circuit headquarters east of it — Boston, New York, Philadelphia, Richmond, Cincinnati, and Atlanta — take Ashburn as their primary data center, while western circuits in New Orleans, Chicago, St. Louis, Denver, and San Francisco route to San Diego.
  2. During the contract, the AOUSC expects to keep moving workloads to the cloud, primarily through Microsoft Azure and Amazon Web Services, which makes the two colocation facilities less a growth mandate than a redundancy floor the judiciary intends to hold while its compute drifts upward.
  3. For bidders, the prize is a decade of sticky federal tenancy that begins only after the current deal expires in July 2029, a patient-money contract built for infrastructure owners with long horizons.

The Administrative Office of the U.S. Courts has published a request for information covering colocation services across two geographically diverse data centers, a process that puts the federal judiciary's existing arrangement with Digital Realty and Csquare in play nearly three years before the current contract runs out.

The agency now operates out of a Digital Realty data center in El Segundo, California, and a Csquare facility in Ashburn, Virginia, under a contract managed by an undisclosed third-party vendor; the deal expires in July 2029, and the RFI asks for a contractor to keep both facilities fully operational under a new contract running until at least July 2032. It is also evaluating whether new data center locations should be considered, and on that point it is explicit: "Please note that AOUSC prefers one location to be near Washington, DC," the RFI states.

Today the split runs along the Mississippi River: circuit headquarters east of it — Boston, New York, Philadelphia, Richmond, Cincinnati, and Atlanta — take Ashburn as their primary data center, while western circuits in New Orleans, Chicago, St. Louis, Denver, and San Francisco route to San Diego. Bidders will want to reconcile one discrepancy, because the routing description places the western service point in San Diego while the Digital Realty facility the agency names sits in El Segundo, a gap that will help determine whether the 2029 rebid is a renewal or a relocation.

During the contract, the AOUSC expects to keep moving workloads to the cloud, primarily through Microsoft Azure and Amazon Web Services, which makes the two colocation facilities less a growth mandate than a redundancy floor the judiciary intends to hold while its compute drifts upward. This publication has argued before that hyperscaler-anchored demand clears as infrastructure while everything else fights for capital; the courts' procurement is the federal version of that split, with Azure and AWS taking the growth and colocation absorbing the residual.

For bidders, the prize is a decade of sticky federal tenancy that begins only after the current deal expires in July 2029, a patient-money contract built for infrastructure owners with long horizons. For Digital Realty and Csquare, the sharper issue is that incumbency carries no presumption of renewal. The RFI's willingness to consider new locations, set against the stated preference for a Washington-area site, means the agency's own language has priced displacement as a live option, and a decade is long enough for a federal tenant to pick up and move.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Omniva names Kushagra Vaid CEO as pivot hires exit

Kuwait-backed neocloud has lost most executives hired for its 2023 AI pivot, including COO Sean Boyle this June, Data Center Dynamics reports.

Infrastructure

Verizon signs AWS AI infrastructure deal worth more than $2 billion

The AWS agreement follows a $1 billion dark fiber deal with Google; Verizon puts all signed contracts at about $4 billion.

Infrastructure

AWS plans up to 15 data center buildings on 890 Missouri acres

The Danville tract has no purchase or start date; Amazon said New Florence will get a $10 billion phased build-out.

Infrastructure

Eatonton 379 files for 520MW Georgia data center campus

The filing includes substations and possible on-site generation with Eatonton.

Infrastructure

Spain proposes 10MW threshold for data-center renewables mandate

The revised proposal keeps the 80% hourly clean-power test and adds a transition period of up to five years.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections