Skip to content
Friday, November 6, 2026 · Today’s edition, 6:30 a.m. ETFri, Nov 6 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Duke Energy's signed large-load agreements rise 200 MW to 7.8 GW

The utility plans a $103 billion buildout heavy on natural gas, with 7.6 GW of the 15.4 GW large-load pipeline still uncontracted.

At a glance

  1. The remaining 7.6 GW of a 15.4 GW large-load pipeline is not under contract.
  2. Chief executive Harry Sideris said the election result would not change the company's growth focus.
  3. For investors in Duke equity or the private funds that finance the buildout, the pace of signings determines how quickly the remaining 7.6 GW becomes contracted revenue.

Duke Energy's signed large-load service agreements rose 200 MW from the first quarter of 2026 to 7.8 GW, the company said on its third-quarter earnings call. The remaining 7.6 GW of a 15.4 GW large-load pipeline is not under contract.

Chief executive Harry Sideris said the election result would not change the company's growth focus. "We have a track record of ... working with both sides of the aisle," Sideris said. "We don't see any changes in that focus or any changes in our ability to work with those that were recently elected."

For investors in Duke equity or the private funds that finance the buildout, the pace of signings determines how quickly the remaining 7.6 GW becomes contracted revenue. Duke has secured about one-third of the $10 billion in equity it plans to issue, chief financial officer Brian Savoy said.

Duke's $103 billion plan calls for 4.8 GW of battery storage and more than 10 GW of new gas capacity by 2031, with about 5 GW already under construction in North Carolina and Indiana. Turbines and gas supply for the new projects are under contract, and the company is exploring pairing a 2.8 GW gas project in North Carolina with a liquefied natural gas storage facility.

North Carolina regulators denied Duke's application for a Certificate of Public Convenience and Necessity for a 255 MW gas generating unit, citing its "staggering" cost and uncertain need, as Private Wealth Daily previously reported. Sideris said the company still considers it "a low-cost solution to help the generation need that we have in the state."

Sideris said negotiations for the remaining 7.6 GW are "going very well, but it's taking longer because of the complexities." He said elected officials "share our goal, too, of protecting our customers and making sure these large loads pay for their fair share."

Duke's $103B plan leans on gas and batteries

Capacity in GW and plan size in $B, targets through 2031

Spending plan$103B
Battery storage by 20314.8 GW
Gas capacity under construction5 GW
Gas project eyed for LNG pairing2.8 GW
Source: Duke Energy Q3 2026 call via Utility Dive

Reported by the Fundraising desk from Utility Dive. Published . Corrections

Related

Infrastructure

North Carolina just made the customer contract part of the permit

The commission refused a 255 MW turbine on a question of who the power serves, and that test now sits under Duke's $103 billion capital plan.

Infrastructure

North Carolina says no to Duke's 255 MW gas plant

A rare denial from the state's deferential utility panel turns gas capacity into a permitting question — and puts a price on time.

Infrastructure

Brookfield infrastructure funds raise $50B in a year

The firm drew $25 billion in the third quarter, bringing year-to-date 2026 fundraising to $123 billion, Commercial Observer reports.

Infrastructure

Oncor expects 20% jump in $47.5B capital plan

Data centers account for the largest share of load growth, Sempra CEO Jeffrey Martin said.

Infrastructure

ING auctions $500 million of data center loans

The auction includes $25 million of debt tied to a Stargate project in New Mexico, with bids due Nov. 19.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections