Drax, Brookfield and Radiant plan up to 1GW data center at Selby

The first 100MW is targeted for the first quarter of 2028 and carries £2.5 billion of a £20 billion estimated build cost.

£2.5bnFirst-phase investment in the Drax data center

At a glance

  1. Brookfield, working through Radiant, its UK-headquartered AI infrastructure platform, estimates total investment in the development could exceed £20 billion ($26.8 billion), including £2.5 billion ($3.4 billion) for phase one.
  2. For an allocator, the number to underwrite is the £2.5 billion initial phase and its conditions, not the £20 billion build that runs past 2031.
  3. Capacity rises to 500MW between 2028 and 2031, with further increases planned after 2031.

Drax, Brookfield and Radiant plan up to 1GW of data center capacity at Drax Power Station in Selby, North Yorkshire, with the first up to 100MW targeted for the first quarter of 2028.

Brookfield, working through Radiant, its UK-headquartered AI infrastructure platform, estimates total investment in the development could exceed £20 billion ($26.8 billion), including £2.5 billion ($3.4 billion) for phase one. Data Center Dynamics first reported the partnership. The project sits inside a joint venture the partners call Brookfield-Qai AI.

For an allocator, the number to underwrite is the £2.5 billion initial phase and its conditions, not the £20 billion build that runs past 2031. Phase one is conditional on planning progress, regulatory and network approvals from government and the system operator, and a signed tenant. No tenant has been named.

Capacity rises to 500MW between 2028 and 2031, with further increases planned after 2031. The proposed site comprises 1,000 acres with 4GW of grid access. It has 2.6GW of active dispatchable generation and cooling systems drawn from the existing wood pellet plant.

Drax Group chief executive Will Gardiner said the site is "one of the few UK sites that can provide large-scale reliable power directly to data center customers by utilizing existing and underutilized generation capacity."

The announcement follows the UK government's rejection of a bid by North Yorkshire Council, the University of York and Drax to develop up to 1.2GW at the same site under the AI Growth Zone scheme, as Private Wealth Daily previously reported. That application failed the scheme's selection criteria. The proposal relies on the station's existing grid access and treats network approvals from the system operator as a condition of the first phase.

Phase one is a tenth of the planned gigawatt

Planned data center capacity at Drax Selby by phase, in MW

100 MWPhase 1 (Q1 2028)500 MWPhase 2 (2028-31)1K MWFull build (post-2031)100 MWPhase 1 (Q1 2028)500 MWPhase 2 (2028-31)1K MWFull build (post-2031)100 MWPhase 1 (Q1 2028)500 MW1K MWFull build (post-2031)
Source: Data Center Dynamics; 1GW = 1,000MW
Show as table
LabelValue (MW)
Phase 1 (Q1 2028)100 MW
Phase 2 (2028-31)500 MW
Full build (post-2031)1K MW

Reported by the Data centers & fiber desk from Data Center Dynamics and Private Wealth Daily archive. Published . Corrections

Related

Infrastructure

UK rejects Drax-backed bid to power 1.2GW data center with biomass

The Selby application failed AI Growth Zone selection criteria; Drax has pivoted to a 100MW project on grid power.

Infrastructure

Dalrymple Finance values Csquare shares at $0

Csquare listed in July at $21, below its marketed range, and trades at $14.90 after raising $1 billion against a $1.35 billion target.

Infrastructure

Uruguay signs $5.7bn Solaria deal for up to 500MW of solar-paired capacity

Phase one pairs a 200MW data center with a 350MW solar project and is due in 2029, according to the newsroom's data basis.

Infrastructure

Anthropic discloses $895.4bn in compute and data center commitments

Google, SpaceX, Amazon and Microsoft account for $396.7 billion of the total, and three of those four contracts are payable regardless of usage.

Infrastructure

Hyperscalers line up $131 billion for AI data center buildout

Microsoft's $25 billion of bonds carry rates of 4.85% to 6.35% and are expected to close Nov. 4.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

Drax, Brookfield and Radiant plan up to 1GW data center at Selby