Digital Realty eyes 1GW data center campus in Kokomo, Indiana

The plan covers three single-story data centers across roughly 3 million sq ft and a possible full buildout by 2033, according to Data Center Dynamics.

At a glance

  1. The plan covers three single-story data centers on 476 acres and could total around 1GW of IT capacity across roughly 3 million sq ft.
  2. Kokomo, the Howard County seat about 50 miles north of Indianapolis, first announced Digital Realty's interest earlier this month.
  3. Digital Realty does not currently operate any data centers in Indiana, and the report does not say how the campus would be powered or what it would cost to build.

Digital Realty has announced it is looking to develop a gigawatt-scale data center campus in Kokomo, Indiana, Data Center Dynamics reported. The plan covers three single-story data centers on 476 acres and could total around 1GW of IT capacity across roughly 3 million sq ft. The campus could be fully built out by 2033.

Kokomo, the Howard County seat about 50 miles north of Indianapolis, first announced Digital Realty's interest earlier this month. The city has said the greenfield site, in Industrial Park North near US 31 and County Road 400 North, will use a closed-loop cooling system to reduce water use, and that no tax abatements will be agreed with any company that develops the site.

Digital Realty does not currently operate any data centers in Indiana, and the report does not say how the campus would be powered or what it would cost to build.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Trump urges data center developers to pay residents a dividend

The Truth Social post backs cash payments; recent offers include $10,000 each in a Pennsylvania township and ten years of credits in a Kansas town.

Infrastructure

Digital Realty breaks ground on 22MW Ankara data center with Rönesans

The first project under the joint venture is due online in 2028; the partnership could eventually reach 200MW, Data Center Dynamics reports.

Infrastructure

Greece drafts rules requiring data centers to source 60% of power from renewables

The same draft would impose a €200,000 per megawatt bank guarantee on grid connection requests and create a €2.3 billion island decarbonization fund.

Infrastructure

Switzerland publishes up to CHF 7bn government cloud tender

Two public-cloud tiers cap at CHF 2 billion each and the private lot at CHF 3 billion; awards due summer 2027.

Infrastructure

gFiber to take over Ting's Colorado Springs dark fiber lease

Terms were not disclosed; Ting will keep serving Colorado Springs customers until the transition completes, no later than June 30, 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections