Data center project stops rise to 16 in Q3

Local governments accounted for 11 of the 16, and 46 of 47 ballot measures passed to limit or ban development, Relae said.

$64Bplanned data center investment stopped in Q3

At a glance

  1. The firm estimated the planned investment behind the cancellations at $64 billion.
  2. Local governments did most of the stopping: seven projects drew formal denials and four were blocked by zoning bans, while developers withdrew the other five, Relae said.
  3. For allocators, Relae's analysis adds the project team's engagement record to the diligence list alongside interconnection position and offtake.

Sixteen data center projects were stopped in the third quarter, up from seven in the third quarter of 2025, according to research firm Relae. The firm estimated the planned investment behind the cancellations at $64 billion.

Local governments did most of the stopping: seven projects drew formal denials and four were blocked by zoning bans, while developers withdrew the other five, Relae said. ESG Dive reported the quarterly counts on Nov. 19. Construction Dive reported the same figures on Nov. 23.

For allocators, Relae's analysis adds the project team's engagement record to the diligence list alongside interconnection position and offtake. The firm found a lack of transparency on water use, noise or local hiring was a leading or secondary concern in 34 of the 44 stopped projects it reviewed.

In the same election season, 46 of 47 local data center ballot measures passed to limit or ban development in jurisdictions across 10 states, Relae said. An NBC exit poll cited by the firm found 76% of voters opposed new data centers in their communities, and 56% said the issue was a crucial or major factor in choosing a congressional candidate.

Relae cautioned against reading the results as a verdict on artificial intelligence. “Data centers have moved to the center of American politics,” the firm wrote, adding that public views have turned more negative and become material for stump speeches, attack ads and ballot measures.

As Private Wealth Daily previously reported, large-load tariffs are emerging as a credit screen for data center projects. Relae's Q3 numbers add a second screen at the local level: a project can hold an interconnection position and an anchor tenant and still lose its permit.

Local governments blocked 11 of the 16 stopped projects

Data center projects stopped in Q3, by who stopped them (count of projects)

PartValue (projects)Share
743.8%
425%
531.3%
Source: Relae, via Construction Dive and ESG Dive
Data centers have moved to the center of American politics.Relae, in its research blog

Reported by the Data centers & fiber desk from Construction Dive, ESG Dive and Relae research blog, as reported by Construction Dive and ESG Dive. Published . Corrections

Related

Infrastructure

Senate passes 62-33 bill to shift grid costs onto data centers

The bill would apply FERC-set protections to projects above 20MW and expand federal authority over interstate transmission permits.

Infrastructure

Large-load tariffs are becoming the data center credit screen

Collateral, minimum billing demand and exit fees are turning utility rate schedules into the first test every project in the queue has to clear.

Digital Assets

Nov. 3 midterms will decide SEC oversight and crypto's tax bills

CoinDesk's State of Crypto reads the House as likely to flip and the Senate as a tossup, with two tax bills and agency rulemaking the near-term tracks.

Infrastructure

Apollo and Goldman price $44 billion GPU notes for SpaceX

Lease schedules on the Nvidia Vera Rubin chips are expected to begin after delivery in the first half of 2027.

Infrastructure

Cogent agrees to sell three data centers to Saragon for $35 million

The deal adds sites in Omaha, Tacoma and Cheyenne and is expected to close in the first quarter of 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections