At a glance
- The firm estimated the planned investment behind the cancellations at $64 billion.
- Local governments did most of the stopping: seven projects drew formal denials and four were blocked by zoning bans, while developers withdrew the other five, Relae said.
- For allocators, Relae's analysis adds the project team's engagement record to the diligence list alongside interconnection position and offtake.
Sixteen data center projects were stopped in the third quarter, up from seven in the third quarter of 2025, according to research firm Relae. The firm estimated the planned investment behind the cancellations at $64 billion.
Local governments did most of the stopping: seven projects drew formal denials and four were blocked by zoning bans, while developers withdrew the other five, Relae said. ESG Dive reported the quarterly counts on Nov. 19. Construction Dive reported the same figures on Nov. 23.
For allocators, Relae's analysis adds the project team's engagement record to the diligence list alongside interconnection position and offtake. The firm found a lack of transparency on water use, noise or local hiring was a leading or secondary concern in 34 of the 44 stopped projects it reviewed.
In the same election season, 46 of 47 local data center ballot measures passed to limit or ban development in jurisdictions across 10 states, Relae said. An NBC exit poll cited by the firm found 76% of voters opposed new data centers in their communities, and 56% said the issue was a crucial or major factor in choosing a congressional candidate.
Relae cautioned against reading the results as a verdict on artificial intelligence. “Data centers have moved to the center of American politics,” the firm wrote, adding that public views have turned more negative and become material for stump speeches, attack ads and ballot measures.
As Private Wealth Daily previously reported, large-load tariffs are emerging as a credit screen for data center projects. Relae's Q3 numbers add a second screen at the local level: a project can hold an interconnection position and an anchor tenant and still lose its permit.
Local governments blocked 11 of the 16 stopped projects
Data center projects stopped in Q3, by who stopped them (count of projects)
| Part | Value (projects) | Share |
|---|---|---|
| 7 | 43.8% | |
| 4 | 25% | |
| 5 | 31.3% |
Data centers have moved to the center of American politics.Relae, in its research blog
Reported by the Data centers & fiber desk from Construction Dive, ESG Dive and Relae research blog, as reported by Construction Dive and ESG Dive. Published . Corrections