Damac Bangkok Leak Puts Oil in Drains, Draws Monitoring

Thirty-two cubic meters of contaminated water are out of Bangkok's drain system, but the permitting record at Damac Digital's BKK 01 site is only beginning.

At a glance

  1. Local media traced the source to Damac Digital Thailand's BKK 01 facility on Rama 9 Road.
  2. Cleanup crews deployed oil-absorbing booms to stop the spread, then applied an environmentally friendly solution to break down the oil, the pollution agency said.
  3. Damac Digital is the data center arm of UAE-based property firm Damac and was formerly known as Edgnex.

An oil leak at a Bangkok data center has contaminated 32 cubic meters of water in the city's drain system, and Thailand's Pollution Control Department said Tuesday the leak had been contained and that it would continue to monitor the area. Local media traced the source to Damac Digital Thailand's BKK 01 facility on Rama 9 Road. The Nation reported that residents raised the alarm on Monday evening after noticing oil and chemical odors rising from their drains.

Cleanup crews deployed oil-absorbing booms to stop the spread, then applied an environmentally friendly solution to break down the oil, the pollution agency said. Damac Digital's contractors removed the contaminated water and sludge from the system. An inspection after the cleanup found no volatile organic compounds or hydrogen sulphide in the air.

Damac Digital is the data center arm of UAE-based property firm Damac and was formerly known as Edgnex. Hussain Sajwani founded the company in 2021, and its first operations were at a 12MW campus in Riyadh. The Bangkok project was announced in 2024 as two 10MW data center buildings, which makes BKK 01 one of the company's newer urban bets.

The 32 cubic meters are already out of the system, but the location, not the volume, is the event. This leak surfaced in a residential neighborhood's drains rather than in an industrial outfall, and the response began with what neighbors could smell. Damac Digital is asking Bangkok to accept a pair of 10MW buildings on a road where people live close enough to notice. The pollution agency's monitoring will check the air and water; the permitting record carries no such cleanup schedule. For investors pricing data center risk in dense cities, that line is the premium.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Damac and Vodafone triple Izmir data center budget to $300 million

The Aegean facility opens at 4MW and aims for 20MW, a downshift from the original plan that lets demand set the pace.

Infrastructure

Enetron Park announces 250MW Pyhäjoki zoning approval despite municipal board rejection

The developer says construction begins in early 2028 while board minutes record a 5-2 vote rejecting planning for the project.

Infrastructure

Digital Realty buys a permitting queue in Turkey

The Ankara joint venture is a bet that in an emerging market the scarce input is a local partner who has already cleared ground, power, and permits.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections