CyrusOne and KEPCO top out 48MW Osaka data center

OSK1's first phase is due online in the first quarter of 2028.

At a glance

  1. The companies marked the milestone with a Jōtōshiki ceremony, in which gold and silver bolts are driven into the final steel beam.
  2. Osaka's 48MW is 8% of the venture's 600MW IT capacity target, leaving roughly a dozen more facilities of comparable capacity to reach the goal.
  3. CyrusOne, owned by KKR, operates or is developing more than 40 data centers across the US and Europe.

CyrusOne and Kansai Electric Power Co. said this week that OSK1, their first data center in Japan, has topped out its steel structure at an Osaka site planned for 48MW of IT capacity.

The companies marked the milestone with a Jōtōshiki ceremony, in which gold and silver bolts are driven into the final steel beam. Ground was broken in September 2024. The first phase is due online in the first quarter of 2028.

Osaka's 48MW is 8% of the venture's 600MW IT capacity target, leaving roughly a dozen more facilities of comparable capacity to reach the goal. The joint venture, announced in May 2023, has said it will invest at least ¥1 trillion ($7 billion) over the next decade and targets 900MW of business scale.

CyrusOne, owned by KKR, operates or is developing more than 40 data centers across the US and Europe. Osaka is its first expansion into Asia. KEPCO owns generation plants totaling more than 35GW and controls ISP Optage and real estate developer Kanden. The venture has said it aims to develop in Tokyo and other major Japanese markets.

Osaka's 48MW is 8% of the venture's 600MW goal

Planned IT capacity at OSK1 against the joint venture's 600MW IT capacity target, in MW

  • Actual
  • Target
  • OSK1, Osaka48 MW of 600 MW · 8%
Source: Data Center Dynamics
Show as table
ItemActualTargetOf target
OSK1, Osaka48 MW600 MW8%

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

KKR and RWE close £12bn UK offshore wind financing

Equity from both sponsors, international lender debt and £1bn from the UK National Wealth Fund back the two Norfolk Vanguard projects.

Infrastructure

ING auctions $500 million of data center loans

The auction includes $25 million of debt tied to a Stargate project in New Mexico, with bids due Nov. 19.

Infrastructure

OMS Group raises $1.03bn for four cable-laying vessels

Atradius and Export Finance Norway back the export credit tranche, and $120 million of trade facilities is still to reach financial close.

Infrastructure

Apollo-backed Vaultica among bidders for Retelit data centers

Ardian, Macquarie and Rai Way also submitted non-binding offers for the 38 Italian data centers plus an Austrian site, valued at about €700 million.

Infrastructure

Senate passes 62-33 bill to shift grid costs onto data centers

The bill would apply FERC-set protections to projects above 20MW and expand federal authority over interstate transmission permits.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

CyrusOne and KEPCO top out 48MW Osaka data center