CEQA can add years to California data center schedules

DLA Piper partner Andrew Brady writes that the law's anti-segmentation rule ties later phases to the first discretionary approval.

At a glance

  1. The California Energy Commission projects statewide data center demand could reach approximately 4.5 gigawatts by 2040, more than four times the roughly 1 gigawatt it estimates today.
  2. CEQA, the 1973 statute, requires public agencies to evaluate and publicly disclose environmental impacts before discretionary entitlements can be approved.
  3. For underwriters, the key provision is anti-segmentation, which requires the whole project and future phases to be analyzed if any part needs a discretionary approval.

Once power and water are settled, the California Environmental Quality Act can add years to a data center schedule and shapes its cost and risk, writes DLA Piper partner Andrew Brady in Data Center Dynamics. The California Energy Commission projects statewide data center demand could reach approximately 4.5 gigawatts by 2040, more than four times the roughly 1 gigawatt it estimates today.

CEQA, the 1973 statute, requires public agencies to evaluate and publicly disclose environmental impacts before discretionary entitlements can be approved. It does not bar projects with significant impacts. It sets the process by which they are studied, modified and entitled. Data centers' energy load, water-cooled infrastructure and industrial footprints touch nearly every environmental category the law was written to examine.

For underwriters, the key provision is anti-segmentation, which requires the whole project and future phases to be analyzed if any part needs a discretionary approval. Most California data center projects trigger at least one such approval, typically a conditional use permit, design review or zoning change. A first-phase approval therefore sets entitlement risk for later phases on a phased campus, and diligence should establish which approvals the first phase pulls in.

A site can avoid the statute only if its approvals are ministerial or fully by right. Brady writes that such sites are rare. They are most likely on industrially zoned land with older codes that permit industrial uses broadly, and they are difficult to find.

His prescription is to build CEQA into site strategy from the outset rather than treat it as a compliance step near the finish. He applies it to smaller facilities and to location-sensitive infrastructure that must be built in California to serve the market, not only to large campuses.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Nokia, Nscale, Skeleton, Telia and Verda form Nordic AI gigafactory consortium

The group says it intends to bid under the European High-Performance Computing Joint Undertaking's call for AI gigafactory consortia.

Infrastructure

Amazon commits $7bn to India renewables with 934MW of PPAs

The four wind and solar deals add to $4 billion of renewable capacity Amazon has already contracted in India.

Infrastructure

Mount Thor raises $45m to build Apple-silicon AI cloud

The San Francisco company will offer access to bare-metal Apple hardware and virtual machines for research labs and AI companies.

Infrastructure

Orange seeks partners for 24-pair ReuNION leg to Singapore

Phase one to South Africa, carrying 320 Tbps across 16 fiber pairs, has a provisional launch expected in early 2029.

Infrastructure

US data center construction falls to 8.4GW in Q3

October starts of 4.6GW put the fourth quarter on pace for a record, Cleanview says.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections