XTX Markets launches 22.5MW data center in Finland

The quant trader has spent more than €400 million on the Kajaani site and says permitting delays leave power for a third building uncertain.

At a glance

  1. The company has spent more than €400 million ($437.7 million) and expects a second building to come online in 2027.
  2. The 15,000-square-meter facility, reported by Data Center Dynamics, will run deep learning that forecasts prices for global financial instruments.
  3. Most of the construction spending has gone to Finnish companies, and XTX is building compute for its own use rather than leasing capacity to third parties.

XTX Markets launched a 22.5MW data center in Kajaani, Finland, its first, on a 193-hectare site. The company has spent more than €400 million ($437.7 million) and expects a second building to come online in 2027.

The 15,000-square-meter facility, reported by Data Center Dynamics, will run deep learning that forecasts prices for global financial instruments. XTX said the work had not previously been run on compute housed in its own data center infrastructure. The firm had leased space across Europe and moved 417 petabytes of storage in one six-week stretch during the migration.

Most of the construction spending has gone to Finnish companies, and XTX is building compute for its own use rather than leasing capacity to third parties. That means Kajaani does not generate contracted offtake revenue; the investment rests on XTX's own trading economics. For advisors and allocators tracking XTX, the due-diligence question is whether the third building, due in 2028, will be ready if the firm's compute needs grow.

Power for the third building, due for completion in 2028, remains uncertain because of expropriation permitting delays, the company said. Chief operating officer Mike Irwin said, "Expropriation permits for grid development that once took months can now take years." Without meaningful government engagement, future investment decisions would be called into question, he said. XTX remains willing to contribute financially to infrastructure solutions that benefit Finland more broadly, Irwin said.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Gimlet Cloud to deploy 100MW of Cerebras wafer-scale compute for inference

The first data center under the agreement is expected online later this year, and the coverage names no site, utility, or contract value.

Digital Assets

AMM-correlated-pairs debate turns on permission

The XTX counterpoint concedes the mechanism; who gets to provide liquidity decides whether tokenized equities matter.

Infrastructure

Promera buys B&G Energy for data center electrical work

The Irish contractor installs low-, medium- and high-voltage power systems and controls linking generators, UPS and battery storage.

Infrastructure

Applied Digital readies first 25MW hall at Polaris Forge 2

Base-build commissioning is complete for 75MW of the campus's first 150MW building, with 50MW still to be fitted out.

Infrastructure

Exaion signs $79 million take-or-pay GPUaaS contract

The four-year deal runs on Nvidia HGX B300 servers, while QumulusAI separately signed a ten-year, 2MW colocation agreement.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

XTX Markets launches 22.5MW data center in Finland