West Virginia keeps the MARL docket on its first-quarter clock

Route and need questions for NextEra's PJM-selected line now have to be resolved without a pause, even as staff ask for more time.

At a glance

  1. The stay request came from the commission's own staff, and NextEra had already said it would accept a delay while arguing that one probably was not necessary.
  2. The commission denied the motion on the grounds that the circumstances did not justify stretching the schedule, leaving route and need questions to be resolved on the state's calendar with a final decision expected in the first quarter of next year, according to local media.
  3. As this publication has argued, PJM's greenlights clear the queue, not the site; this ruling keeps the site's calendar in motion, which is preferable to an open-ended wait for investors trying to price when the line actually gets built.

West Virginia's Public Service Commission has refused to pause its review of NextEra's MidAtlantic Resiliency Link, keeping the PJM-selected transmission project pointed at a first-quarter decision even though commission staff had asked for more time to examine the line's roughly 60-mile path through the state, its underlying need, and a June FERC order tightening interconnection rules for large loads.

The stay request came from the commission's own staff, and NextEra had already said it would accept a delay while arguing that one probably was not necessary. In comments ahead of the decision, the company leaned on the project's pedigree: MARL was selected by PJM in 2023 as part of its regional transmission expansion plan, which NextEra describes as a regional planning project, not a network upgrade created for a specific data center interconnection. The FERC order is aimed at large-load interconnection requests, while lines selected through the market operator's planning process sit outside its scope.

The commission denied the motion on the grounds that the circumstances did not justify stretching the schedule, leaving route and need questions to be resolved on the state's calendar with a final decision expected in the first quarter of next year, according to local media.

That refusal is the disciplined outcome: tying MARL's schedule to the FERC order would have let a data-center interconnection policy reset the clock on a project PJM had already deemed necessary regionally, while the state docket becomes the only remaining gate, and it has a date. As this publication has argued, PJM's greenlights clear the queue, not the site; this ruling keeps the site's calendar in motion, which is preferable to an open-ended wait for investors trying to price when the line actually gets built.

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

FERC's cheapest route to PJM capacity runs through governance

A Harvard Law argument says the commission can reshape who decides PJM's planning protocol, and the amendment path is where transmission capital gets priced.

Infrastructure

Virginia officials ask SCC to deny or condition Dominion-NextEra merger

Lt. Gov. Ghazala Hashmi said the merger is "not in the best interest of Virginians"; the SCC plans a January decision.

Infrastructure

Bain projects $5tn to $6.5tn data center spending through 2030

Power availability, electrical labor and local opposition are the near-term constraints, not capital.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections