Skip to content
Monday, October 26, 2026 · Today’s edition, 6:30 a.m. ETMon, Oct 26 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

US wind orders hit 2.8 GW in Q2 before tax credit cutoff

Wood Mackenzie keeps a 39 GW onshore outlook through 2030 and says more than half of the 2026–2028 pipeline is operating or under construction.

At a glance

  1. The deadline comes from the One Big Beautiful Bill Act, which President Donald Trump signed last year.
  2. For allocators, the two dates sort the U.S. wind pipeline into separate risk buckets.
  3. Installations ran well ahead of orders in the quarter.

U.S. developers ordered 2.8 GW of wind turbines in the second quarter of 2026, racing to start construction before a July 4 deadline that preserves federal tax credits, Wood Mackenzie reported Monday.

The deadline comes from the One Big Beautiful Bill Act, which President Donald Trump signed last year. It moved up the dates wind and solar projects must meet to keep eligibility for the 45Y clean energy production tax credit and the 48E clean energy investment tax credit. Projects that commenced construction before July 4, 2026, have until Dec. 31, 2030, to be placed in service. Projects that missed that gate must be operating by Dec. 31, 2027, to qualify.

For allocators, the two dates sort the U.S. wind pipeline into separate risk buckets. Projects that missed the July gate must be in service by Dec. 31, 2027, which leaves little more than a year of construction and commissioning. That pushes schedule and turbine delivery to the front of diligence ahead of wind resource. Projects that cleared the gate have until 2030, and their credits rest on the commence-construction test rather than on completion.

Installations ran well ahead of orders in the quarter. The U.S. added about 5 GW of onshore capacity in the second quarter, most of it from the 3.65 GW SunZia project in New Mexico, which the report called the country's largest such project to date.

Wood Mackenzie kept its view that the U.S. wind industry will add 39 GW of onshore new-build capacity by 2030. More than half of the 2026–2028 project pipeline is already operating or under construction, the report said.

"Policy is the variable with the greatest impact on wind installations," Wood Mackenzie analyst Tyler Gifford said.

Offshore is the weaker half of the outlook. Wood Mackenzie counted 5 GW delivering within the next two years and said unfavorable policy limits new development — Trump's executive order pausing new offshore lease sales in federal waters, administration deals to buy back leases previously auctioned, and continuing court efforts to block projects under construction.

Next year, the American Society of Civil Engineers is expected to publish guidelines requiring turbines in tornado-prone areas to meet certain design requirements, which Wood Mackenzie said will raise project costs.

Q2 2026: 5 GW online — 3.65 GW of it SunZia — vs 2.8 GW ordered

U.S. onshore wind, gigawatts, second quarter 2026

  • Onshore capacity installed5 GW
  • SunZia, New Mexico (part of Q2 installs)3.65 GW
  • Turbine orders placed2.8 GW
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
ItemValue (GW)
Onshore capacity installed5 GW
SunZia, New Mexico (part of Q2 installs)3.65 GW
Turbine orders placed2.8 GW

Q2 wind: 5 GW installed vs 2.8 GW ordered — SunZia was 3.65 GW

U.S. onshore wind capacity, gigawatts, second quarter 2026

2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia (part of Q2 installs)2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia (part of Q2 installs)2.8 GWTurbine orders5 GW3.65 GWSunZia (part of Q2 installs)
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
LabelValue (GW)
Turbine orders2.8 GW
Capacity installed5 GW
SunZia (part of Q2 installs)3.65 GW

Q2 2026: 5 GW installed vs 2.8 GW ordered; SunZia alone was 3.65 GW

U.S. onshore wind, gigawatts, second quarter 2026

5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GWCapacity installed3.65 GW2.8 GWTurbine orders
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
LabelValue (GW)
Capacity installed5 GW
SunZia project (New Mexico)3.65 GW
Turbine orders2.8 GW

Q2 2026: 5 GW installed vs 2.8 GW ordered — SunZia alone was 3.65 GW

U.S. onshore wind, gigawatts, second quarter 2026

2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia project (part of installs)2.8 GWTurbine orders5 GW3.65 GWSunZia project (part of installs)2.8 GWTurbine orders5 GW3.65 GWSunZia project (part of installs)
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
LabelValue (GW)
Turbine orders2.8 GW
Capacity installed5 GW
SunZia project (part of installs)3.65 GW

Q2 installs ran to 5 GW vs 2.8 GW of orders — SunZia was 3.65 GW

U.S. onshore wind, gigawatts, second quarter 2026

5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GWCapacity installed3.65 GW2.8 GWTurbine orders
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
LabelValue (GW)
Capacity installed5 GW
SunZia project (New Mexico)3.65 GW
Turbine orders2.8 GW

SunZia's 3.65 GW topped all Q2 U.S. wind turbine orders

U.S. onshore wind capacity, gigawatts, second quarter 2026

2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GWCapacity installed3.65 GWSunZia project (New Mexico)2.8 GWTurbine orders5 GW3.65 GWSunZia project (New Mexico)
Source: Wood Mackenzie via Utility Dive · Q2 2026
Show as table
LabelValue (GW)
Turbine orders2.8 GW
Capacity installed5 GW
SunZia project (New Mexico)3.65 GW

Reported by the Energy Transition desk from Utility Dive and Wood Mackenzie. Published . Corrections

Related

Infrastructure

Planned U.S. natural gas capacity comparable to solar and wind on capacity-factor basis: EDF

Clean energy still accounts for the largest share of planned U.S. power sector development, but nearly 5% of a planned 281.7 GW of clean energy deployment was canceled in 2025, EDF says.

Infrastructure

DOE offers Vistra a $4.2 billion conditional loan for 433 MW of nuclear uprates

The commitment is tied to Vistra's 2.6-gigawatt Meta agreement and would preserve roughly 4 gigawatts of PJM nuclear, with funding awaiting technical, legal, environmental and financial reviews.

Infrastructure

Bain projects $5tn to $6.5tn data center spending through 2030

Power availability, electrical labor and local opposition are the near-term constraints, not capital.

Infrastructure

MISO 120-day load study draws state, Google objections at FERC

Eleven state utility commissions backed OMS's protest; MISO files a cost-allocation framework next month.

Infrastructure

Data center power demand nears 20% a year; procurement is the risk

Transparent Energy's Dustin Scarpa says suppliers price load shape, credit, collateral and start-date certainty, not just scale, into a data center's power contract.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections