Skip to content
Thursday, November 5, 2026 · Today’s edition, 6:30 a.m. ETThu, Nov 5 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Trump grid equipment order draws cost, supply warnings

Energy Department rules are due Dec. 24 and may allow removal of grid equipment already in service.

At a glance

  1. Executive Order 14421 lets Energy Secretary Chris Wright block foreign-produced equipment — or any critical component, software, firmware, digital service, maintenance service, or remote-access capability — that poses an 'undue risk' to national security.
  2. For anyone underwriting regulated utility capex or the suppliers that fill those orders, the removal-and-replacement clause reaches backward: equipment already in service could become an unplanned cost under the Dec. 24 rules.
  3. Industry comments to DOE showed broad support for the order's intent and wide concern over implementation.

Stakeholders back the intent of President Donald Trump's Aug. 26 order letting the Energy Department block foreign-made grid equipment. They warn it could add cost and delay procurement, Utility Dive reported Nov. 4.

Executive Order 14421 lets Energy Secretary Chris Wright block foreign-produced equipment — or any critical component, software, firmware, digital service, maintenance service, or remote-access capability — that poses an 'undue risk' to national security. The risk includes intentional sabotage or supply-chain disruption. The order also lets the secretary order removal and replacement of equipment already in service. DOE sought industry comment in September and must publish implementing rules by Dec. 24.

For anyone underwriting regulated utility capex or the suppliers that fill those orders, the removal-and-replacement clause reaches backward: equipment already in service could become an unplanned cost under the Dec. 24 rules. Utilities are projected to spend more than $1 trillion on grid upgrades through 2030 and are racing to secure equipment contracts amid rising manufacturer backlogs.

Industry comments to DOE showed broad support for the order's intent and wide concern over implementation. Some respondents said security standards, especially for software that would enable remote access, can matter more than country of origin. The vast majority of respondents who addressed 'function over origin' favored functional controls over a product's origin, according to data compiled by industry analyst Brendon Shank. Many respondents also asked DOE to phase in new compliance rules and to let some vendors 'prequalify' as trustworthy.

The National Electrical Manufacturers Association, which represents more than 300 electrical equipment manufacturers, said in comments to DOE the supply base is already strained at current volumes. "Supply chains are already approaching a breaking point for many categories of electrical industry products," the group said, adding that evaluating, redesigning and producing equipment to new specifications takes time, money and resources during a period of high demand and longer lead times than in eras of steadier electricity growth.

The Dec. 24 rules will determine whether prequalification and phasing give manufacturers a route through the screening, or whether country of origin becomes the gate.

The order's road to a Dec. 24 rule

Key dates for Executive Order 14421 implementation

  1. Aug. 26Executive Order 14421 issued (Completed)
  2. SeptemberEnergy Department seeks industry comment (Completed)
  3. Dec. 24Implementing rules and regulations due (Current stage)
Source: Utility Dive; Executive Order 14421
Show as table
DateEventDetail
Aug. 26Executive Order 14421 issued
SeptemberEnergy Department seeks industry comment
Dec. 24Implementing rules and regulations due
Supply chains are already approaching a breaking point for many categories of electrical industry products.National Electrical Manufacturers Association, in comments to the Energy Department

Reported by the Energy Transition desk. Published . Corrections

Related

Infrastructure

Mark Christie urges amendments to Senate permitting bill

The former FERC chairman says SB 5653 would let FERC order a transmission line built in any state, overriding a state's own siting decision.

Infrastructure

DOE's $1.9 billion buys grid speed, not new corridors

The SPARK package funds conductors and grid-enhancing technology on lines that already exist, moving the marginal federal transmission dollar off greenfield corridors and onto assets the data center buildout can actually schedule.

Infrastructure

Alliant Energy expects 1GW of data center contracts in six months

The Wisconsin utility raised its 2027-2030 capital plan 19% to $15.9 billion and says the contracted book includes Google, Meta and QTS.

Infrastructure

Renewable Innovations joins DOE fuel cell project for AI data centers

The three-year project led by the National Laboratory of the Rockies includes an 800VDC field demonstration at a Sky Data Centers site in California.

Infrastructure

PG&E cuts $2 billion in grid investment

Canary Media asks whether the utility's lower grid spending slows California's clean energy buildout.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections