At a glance
- Data Center Dynamics first reported the brand launch.
- The split leaves Cirion's telecommunications and data center operations as two independent companies, with the telecom business keeping the Cirion name.
- For advisors and allocators, the separation means underwriting Datrix on power capacity and square meters rather than blended telecom-and-real-estate cash flow.
Cirion Technologies, backed by Stonepeak, has spun its data center business into a standalone company called Datrix with 12 carrier-neutral facilities in six Latin American markets. Data Center Dynamics first reported the brand launch.
The split leaves Cirion's telecommunications and data center operations as two independent companies, with the telecom business keeping the Cirion name. Santiago Londoño runs the connectivity business and Nelson Fonseca, who joined in 2024 as president of the data center unit, is chief executive of Datrix. No financial terms were disclosed.
For advisors and allocators, the separation means underwriting Datrix on power capacity and square meters rather than blended telecom-and-real-estate cash flow. Its stated targets are hyperscale providers, cloud providers, content platforms and AI workloads.
In Brazil, Datrix operates four named facilities, including a Rio de Janeiro campus with 89MW, a São Paulo site with 20MW and a Curitiba site with 1MW. The Rio campus spans about 22,100 square meters, SAO1 about 19,800 square meters and CUR1 about 9,100 square meters. Outside Brazil the platform operates in Buenos Aires, Santiago, Bogotá, Quito and Lima.
Cirion itself was spun out of Lumen by Stonepeak in 2022 and runs more than 105,000 kilometers of fiber-optic network in 20 countries. Stonepeak reported $81.9 billion in regulatory assets under management in a Form ADV filed with the SEC on Oct. 5.
Rio campus holds more than four times Sao Paulo's power
Installed power capacity per named Brazilian campus, in MW
- Rio de Janeiro (RIO1/RIO2)89 MW
- Sao Paulo (SAO1)20 MW
- Curitiba (CUR1)1 MW
Show as table
| Item | Value (MW) |
|---|---|
| Rio de Janeiro (RIO1/RIO2) | 89 MW |
| Sao Paulo (SAO1) | 20 MW |
| Curitiba (CUR1) | 1 MW |
Reported by the Data centers & fiber desk from Data Center Dynamics and Form ADV (SEC IAPD). Published . Corrections