Southern Co. flags potential $100B five-year capital plan

The utility added $4 billion to an $81 billion plan, with gas and nuclear uprates and new generation able to lift it to $100 billion.

$100BTop end of Southern Co.'s five-year capital plan

At a glance

  1. The additions include 400 MW of uprates at existing natural gas plants and an expansion of the Southeast Connector gas pipeline.
  2. For allocators, Southern's large-load contracts contain minimum bills covering at least 100% of the cost entering the system, so recovery does not depend on a customer reaching its expected growth rate.
  3. The capital plan lands after a midterm election that changed the regulatory map in Georgia and Washington.

Southern Co. told investors its five-year capital plan could reach $100 billion, versus an $81 billion base set in February that it has since raised by about $4 billion, Utility Dive reported.

The additions include 400 MW of uprates at existing natural gas plants and an expansion of the Southeast Connector gas pipeline. Georgia Power, Southern's utility subsidiary, also received approval during the quarter for an agreement with Google to expand nuclear capacity through uprates over the next several years, CFO David Poroch said.

For allocators, Southern's large-load contracts contain minimum bills covering at least 100% of the cost entering the system, so recovery does not depend on a customer reaching its expected growth rate. "Before the kilowatt moves over the meter, we are recovering our costs embedded in those minimum bills," CFO David Poroch said. About $15 billion separates the $85 billion implied by the February base plus the third-quarter additions from the $100 billion figure. That slice is the additional generation, and it depends on winning new-build bids and on regulators authorizing the plants.

The capital plan lands after a midterm election that changed the regulatory map in Georgia and Washington. Anger over electricity bills helped Democrats take control of Congress and win Georgia's governor's office and a majority on the Public Service Commission, Utility Dive reported, and Democrats won two Georgia PSC seats, as Private Wealth Daily previously reported. CEO Chris Womack said he has not heard talk of retroactive data center freezes or of looking back at signed contracts. "I feel pretty confident about what we have in place," he said.

Womack also listed large loads that are not data centers as continued drivers of growth in the South, including projects from Airbus, Mitsubishi Power and Audi. Mitsubishi Power plans a major expansion of its gas turbine manufacturing plant in Savannah, Georgia, which he said will help meet rising generation needs.

Southern is competing for new generation contracts in Alabama and Georgia with company-owned resources. Those awards, followed by authorization from the respective regulators, determine how much of the $100 billion is actually built.

A $15B slice hinges on winning new-build bids

Five-year capital plan in $B: February base, third-quarter additions and potential generation

  • Added
  • Taken away
  • Total
  • February base$81B
  • Q3 additions+$4B
  • Additional generation+$15B
  • Potential plan$100B
Source: Utility Dive; company figures and arithmetic
Show as table
StepChangeRunning total
February base$81B$81B
Q3 additions+$4B$85B
Additional generation+$15B$100B
Potential plan$100B
Before the kilowatt moves over the meter, we are recovering our costs embedded in those minimum billsDavid Poroch, executive vice president and CFO of Southern Co.

Reported by the Energy Transition desk from Utility Dive and Private Wealth Daily archive. Published . Corrections

Related

Infrastructure

The nuclear tariff is the new power contract

Georgia Power's 96-megawatt Google subscription turns an uprate into a copyable utility product while merchant deals keep printing capacity with the price column blank.

Infrastructure

Google buys a nuclear tariff, and 96 megawatts is the receipt

If Georgia's regulators approve the subscription structure, Southern Co. gains a copyable way to sell uprate megawatts to large loads, and every utility with an uprate candidate gets a filing to imitate.

Infrastructure

OpenAI hires a power screen for its buildout

A single remote hire, capped at $385,000, will decide which power options and developer pitches survive contact with OpenAI's construction schedule.

Infrastructure

Dominion Virginia distribution grid load factor is 41%, disclosure shows

Its transmission median is about 33% against a U.S. systemwide load factor of about 60%, Grid Strategies says.

Infrastructure

AirTrunk signs Hunter renewables exclusivity with European Energy

Solar and battery output are expected in 2030, with wind following in 2032.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections