Soluna buys Texas land for 300MW AI site

The purchase pairs a 397-acre plot with a wind farm Soluna already owns, putting behind-the-meter power at the center of its pitch to AI customers.

At a glance

  1. The land sits next to the 150MW Briscoe onshore wind farm Soluna bought in April, and the wind farm's substation is directly across from the new property, a layout that positions Dorothy 3 for behind-the-meter power and lets a data center bypass the usual utility handoff.
  2. John Belizaire, Soluna's chief executive, framed the purchase as a way to shrink the timeline customers care about, since AI tenants ask how fast they can reach power and owning the land removes one variable from the answer, he said.
  3. At its ceiling, the new campus alone would be larger than the entire operating fleet, which is why the modern data center buildout turns on power as the binding constraint: in Texas the ERCOT interconnection queue decides which projects actually get built.

Soluna has acquired a 397-acre plot in Briscoe County, Texas, for the third phase of its Dorothy data center complex and expects the site to host up to 300MW, Data Center Dynamics first reported.

The land sits next to the 150MW Briscoe onshore wind farm Soluna bought in April, and the wind farm's substation is directly across from the new property, a layout that positions Dorothy 3 for behind-the-meter power and lets a data center bypass the usual utility handoff.

John Belizaire, Soluna's chief executive, framed the purchase as a way to shrink the timeline customers care about, since AI tenants ask how fast they can reach power and owning the land removes one variable from the answer, he said.

The two-part bargain

Dorothy 3 becomes the largest single project on Soluna's books, though it is not the company's first site; the company operates 192MW today and counts 11 data center sites in various stages of development, among them the 187MW Project Rosa, the 50MW Dorothy I A and B, the 48MW Dorothy II, the 25MW Project Sophie in Kentucky and the 2MW Grace site in Texas.

At its ceiling, the new campus alone would be larger than the entire operating fleet, which is why the modern data center buildout turns on power as the binding constraint: in Texas the ERCOT interconnection queue decides which projects actually get built. Owning land does not clear that queue, but it gives a developer the one thing that makes waiting tolerable — control over the site and the generation behind it.

Soluna's April purchase of the wind farm was the first half of that bargain, and the Dorothy 3 land acquisition is the second. Together they let the company offer a customer a substation directly across the way, a renewable plant on the balance sheet, and 397 acres to build on, rather than a promise to assemble those pieces later.

The risk is the gap between a 300MW ceiling and an executed offtake agreement. Soluna describes itself as an AI and cryptocurrency data center developer, and the announcement is aimed at AI customers evaluating sites, but the announcement itself is not a customer commitment.

What the company is selling is a schedule, and the schedule only matters if someone signs behind it. Until an offtake agreement lands, 300MW remains the ceiling on that schedule rather than a project.

Soluna data center capacity, by project (MW)

  • Dorothy 3 (up to)300 MW
  • Total operating fleet192 MW
  • Project Rosa187 MW
  • Dorothy I A & B50 MW
  • Dorothy II48 MW
  • Project Sophie25 MW
  • Grace2 MW
Source: Soluna via Data Center Dynamics
Show as table
ItemValue (MW)
Dorothy 3 (up to)300 MW
Total operating fleet192 MW
Project Rosa187 MW
Dorothy I A & B50 MW
Dorothy II48 MW
Project Sophie25 MW
Grace2 MW
What the company is selling is a schedule, and the schedule only matters if someone signs behind it.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Soluna and Applied Digital agree 50MW Texas data center joint venture

Applied is expected to hold 51% and supply capital; ChronoScale has signed a non-binding letter of intent to lease the capacity.

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported $45 billion contract would double Anthropic's committed capacity at Monarch to 920MW; Microsoft already holds 1.35GW there.

Infrastructure

Soluna files for 112MW Kati II data center in Willacy, Texas

The Texas filing estimates $471.8 million for a single 471,884 sq ft building and gives no construction timeline.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections