Skybox and Prologis file for fourth and largest Hutto data center

The 846,300 sq ft single-story building would be the biggest at the PowerCampus site, with construction set for January 2027 and $550 million from Skybox.

At a glance

  1. The application, reported by Data Center Dynamics, describes an 846,300 sq ft single-story core-and-shell structure at 3399 County Road 132 with a future use as a data center, a construction window running from January 2027 to October 2028, and a $550 million investment from Skybox.
  2. The site owner is listed as Hutto Data Center Campus, LLC, an affiliate sharing an address with Prologis, the real estate firm that has worked with Skybox since early 2021, when the two filed to convert an empty Prologis warehouse in Chicago into a data center.
  3. Skybox filed for Hutto 1 in October 2023, then Hutto 2 in April 2024 and Hutto 3 in May 2024—three applications inside seven months for parcels along the same county road—followed by a gap of roughly two and a half years before this week's fourth.

Skybox and Prologis filed this week with the Texas Department of Licensing and Regulation for Skybox Hutto 4, the fourth and largest building at their data center campus in Hutto, Williamson County, about 28 miles northeast of Austin. The application, reported by Data Center Dynamics, describes an 846,300 sq ft single-story core-and-shell structure at 3399 County Road 132 with a future use as a data center, a construction window running from January 2027 to October 2028, and a $550 million investment from Skybox.

Building 4 is the largest of the four filed so far: the first two Hutto buildings were each listed at 235,720 sq ft and the third at 492,350, making the new application about 72 percent larger than Hutto 3, bigger than Hutto 1 and Hutto 2 combined, and roughly 88 percent of the square footage of all three earlier phases. It is also the only single-story building in the sequence, whereas its predecessors are set to span two stories—a design difference that points to a larger land take per square foot of floor area without explaining why the developer moved to one level.

The site owner is listed as Hutto Data Center Campus, LLC, an affiliate sharing an address with Prologis, the real estate firm that has worked with Skybox since early 2021, when the two filed to convert an empty Prologis warehouse in Chicago into a data center.

Hutto 4 is nearly as large as the first three Skybox buildings combined

Filed floor area by building, Skybox/Prologis PowerCampus, Hutto, Texas

235.7K sq ftHutto 1235.7K sq ftHutto 2492.4K sq ftHutto 3846.3K sq ftHutto 4235.7K sq ftHutto 1235.7K sq ftHutto 2492.4K sq ftHutto 3846.3K sq ftHutto 4Hutto 1Hutto 2Hutto 3846.3K sq ftHutto 4
Source: Texas Dept. of Licensing and Regulation filings via Data Center Dynamics · Oct 2026
Show as table
LabelValue (sq ft)
Hutto 1235.7K sq ft
Hutto 2235.7K sq ft
Hutto 3492.4K sq ft
Hutto 4846.3K sq ft

Three filings, then a two-and-a-half-year pause

Skybox filed for Hutto 1 in October 2023, then Hutto 2 in April 2024 and Hutto 3 in May 2024—three applications inside seven months for parcels along the same county road—followed by a gap of roughly two and a half years before this week's fourth. The coverage does not say what accounts for the pause, or whether the first three buildings are under construction or complete. Permitting, power procurement, and leasing each run on their own clock, and a licensing application does not say which one is binding, so the filing record alone is thin ground for reading the gap as evidence of demand in either direction.

Skybox and Prologis describe the site as part of PowerCampus, planned for 600MW of IT capacity across 3.88 million sq ft. Divided out, that plan implies about 155 watts of IT load for every square foot of the planned footprint, and the four buildings filed so far total roughly 1.81 million sq ft—a little under half the campus plan—which suggests more applications lie ahead if the build proceeds as drawn. Capacity rather than floor area will decide the outcome; grid access and load-class rules now set returns before a data center signs its first lease.

Hutto is filling in from more than one direction, with Iron Mountain and Colovore also developing sites in the town. Colovore arrives with a Texas program already running, including a $430 million liquid-cooled data center in Fort Worth filed in September. With four Skybox buildings and two competing developers in the same town, the permitting process has its own timetable, and consent is where the next phase's schedule gets set.

Skybox brings a Texas-weighted portfolio to Hutto, with projects in Austin, Dallas, Houston, and Wichita Falls, and the fourth filing extends a development bet that began with Hutto 1 three years ago. Prologis brings the land and the template that has carried the partnership across multiple projects; state licensing records show seven Prologis items, four of them transactions between mid-August and mid-September, and the Hutto arrangement—an affiliate holding the parcel, Skybox developing it—is likely a way for a logistics landlord to convert land into data center development at better than warehouse economics. The coverage does not describe the terms between the two firms.

The occupant is not in the filing

$550 million against 846,300 sq ft works out to roughly $650 a square foot for a core-and-shell building whose fit-out, if any, the filing does not describe. The application is a construction and licensing step, and the coverage identifies no tenant for Hutto 4 and does not say whether one has signed, which leaves the building among the unanchored merchant shells—where assets with a named anchor tenant or a sovereign buyer get infrastructure pricing and unanchored shells wait for a counterparty to appear.

A fifth application within months would make the pause between Hutto 3 and Hutto 4 look like a scheduling artifact. A next filing that waits until Building 4 finishes in October 2028 would mean the campus is being metered out one shell at a time; the concrete date on the calendar is January 2027, when Skybox's construction window opens on the largest building the partners have filed for at Hutto.

A fifth application within months would make the pause between Hutto 3 and Hutto 4 look like a scheduling artifact.

Reported by the Data centers & fiber desk from Data Center Dynamics and PID archive and entity records (internal). Published . Corrections

Related

Infrastructure

Stack Infrastructure affiliate files for second Lancaster data center building

The DFW02B filing carries a $540 million construction budget and a March 2027 to December 2028 schedule.

Infrastructure

Lambda and Sharon AI price GPU-backed debt 317 basis points apart

Lambda's $1bn facility is rated investment grade and priced at 6.78%; Sharon AI's $365m of SPV debt came at 9.95%.

Infrastructure

Colovore files for $430 million liquid-cooled data center in Fort Worth

The Denton County project is scheduled to run from December 2026 to December 2028, with the landowner listed as a likely Hillwood Properties affiliate.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Infrastructure

Telefónica, IQM to install Madrid's first quantum computer by end-2026

The IQM Spark system will give Madrid universities, hospitals and startups direct access to quantum hardware.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections