Resolution No. 1300, in force since Oct. 9, requires new mining connections above 5MW to accept supply the grid can cut without a restoration deadline.

At a glance

  1. Category IV reliability, introduced in February 2026, lets the grid cut supply without limits on frequency or duration and sets no guaranteed restoration deadline.
  2. For an allocator underwriting a mining-linked data center in Russia, diligence now turns to outage terms: no restoration deadline and no limit on interruption frequency or duration.
  3. Applications that fail the technical conditions or fall in territories where a ban also covers Category IV mining are cancelled.

Russia requires new cryptocurrency mining grid connections to use an interruptible power category under Resolution No. 1300, dated Oct. 6 and in force since Oct. 9, Data Center Dynamics reported.

Category IV reliability, introduced in February 2026, lets the grid cut supply without limits on frequency or duration and sets no guaranteed restoration deadline. Russia's Energy Ministry said the measure is meant to keep mining demand from creating electricity and capacity shortages for other consumers, according to PRIME.

For an allocator underwriting a mining-linked data center in Russia, diligence now turns to outage terms: no restoration deadline and no limit on interruption frequency or duration. Where a region exempts Category IV mining, curtailment comes ahead of other Category IV consumers during specified maintenance and emergency restrictions.

Applications that fail the technical conditions or fall in territories where a ban also covers Category IV mining are cancelled. Connection fees are settled against costs the grid company has already incurred, so withdrawal does not necessarily mean a full refund.

The threshold is a maximum load above 5MW at the connection point, counting equipment already connected there, with supply at 6kV or higher from switchgear rated 110kV or above. The resolution also drops the requirement for a separate external power-supply scheme for permanent Category IV connections.

DCD reported in September that Russia banned mining in Moscow, the surrounding region and parts of Kursk through the end of 2032. Russia's digital development ministry has been weighing AI data center sites in Belarus and Kazakhstan amid power constraints, as Private Wealth Daily previously reported.

New mining connections were pushed onto interruptible power

Key dates for Category IV reliability and Resolution No. 1300

  1. Feb 2026Category IV reliability category introduced (Completed)
  2. Oct 6Resolution No. 1300 dated (Completed)
  3. Oct 9Rules in force for new mining connections (Current stage)
Source: Data Center Dynamics; Resolution No. 1300
Show as table
DateEventDetail
Feb 2026Category IV reliability category introduced
Oct 6Resolution No. 1300 dated
Oct 9Rules in force for new mining connections

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Malaysia requires data centers to source 30% renewable power

The Energy Commission is drafting guidelines on how the 30% threshold will be measured, with 5GW of new capacity conditional on it.

Infrastructure

13 states attempted data center moratoriums in 2026

New York, Oregon and Texas have statewide bans, Data Center Dynamics reports.

Infrastructure

Eatonton 379 files for 520MW Georgia data center campus

The filing includes substations and possible on-site generation with Eatonton.

Infrastructure

Kyivstar buys cloud provider GigaCloud for $50 million

About $5 million of the price is tied to operational milestones and capital spending met after close.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

Russia limits new cryptomining grid links to interruptible power