PPL data center pipeline reaches 35.3 GW

PPL's commercial terms with QTS cover about 2 gigawatts at a Salem Township site, with gas plants and fuel cells to follow.

At a glance

  1. On the same call, the utility said it had agreed commercial terms to supply about 2 gigawatts of generation to a QTS data center in Salem Township, Pennsylvania.
  2. Signed load under electric service agreements in PPL Electric's Pennsylvania territory rose 300 megawatts to about 11.4 gigawatts, with 8.5 gigawatts under construction, up 2 gigawatts from the prior quarter.
  3. PPL's large-load tariffs in Pennsylvania and Kentucky require data centers to cover the cost of serving them, so the tariff decides who carries the buildout capex.

PPL's advanced-stage data center pipeline in Pennsylvania reached 35.3 gigawatts in the third quarter, up 3.5 gigawatts from the second, PPL said on its third-quarter earnings call. On the same call, the utility said it had agreed commercial terms to supply about 2 gigawatts of generation to a QTS data center in Salem Township, Pennsylvania.

Signed load under electric service agreements in PPL Electric's Pennsylvania territory rose 300 megawatts to about 11.4 gigawatts, with 8.5 gigawatts under construction, up 2 gigawatts from the prior quarter. PPL said it has connected two data centers and energized 300 megawatts of contracted load that will ramp toward roughly 2 gigawatts. The advance is the utility's 11th consecutive quarterly increase in advanced-stage projects, according to Data Center Dynamics.

PPL's large-load tariffs in Pennsylvania and Kentucky require data centers to cover the cost of serving them, so the tariff decides who carries the buildout capex. Large-load customers will pay for most of the added investment in a $25 billion capital plan for 2027 through 2030, a $2 billion increase tied to an additional gas combined-cycle unit in Kentucky, as Private Wealth Daily previously reported.

The QTS supply deal runs through Invitium Energy, PPL's joint venture with Blackstone Infrastructure in which PPL holds 51%. It began as a non-binding letter of intent, and CEO Vince Sorgi said the two teams are working on a long-form agreement. To serve the site, PPL plans two combined-cycle gas plants alongside fuel cells and battery storage. The fuel cells and batteries could be online as early as 2029, with the gas plants following in 2032 and 2033.

Sorgi said he expects the relationship to extend beyond the first phase. "If they look to expand on that Salem site and/or develop a different site, I would expect that we would be engaged in that process," he said, adding that Invitium is in talks with other customers. In Kentucky, PPL's economic development pipeline grew by 1 gigawatt to 14.7 gigawatts through 2032, including 12.8 gigawatts of data center load.

Sorgi said a further Invitium announcement is "certainly possible" before year-end, without giving a timeline. The nearer milestone is the QTS long-form agreement, which would turn agreed commercial terms into contracted load and put the 2 gigawatts into the service agreement totals behind the pipeline.

If they look to expand on that Salem site and/or develop a different site, I would expect that we would be engaged in that process.Vince Sorgi, CEO of PPL

Reported by the Energy Transition desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

PPL adds $2B to capital plan for Kentucky gas plant

The 645 MW combined-cycle project would enter service in 2032, and PPL says it will file for approval after signing a data center power agreement.

Infrastructure

Alliant Energy expects 1GW of data center contracts in six months

The Wisconsin utility raised its 2027-2030 capital plan 19% to $15.9 billion and says the contracted book includes Google, Meta and QTS.

Infrastructure

Stack Infrastructure affiliate files for second Lancaster data center building

The DFW02B filing carries a $540 million construction budget and a March 2027 to December 2028 schedule.

Infrastructure

Anchor Energy Partners targets €75 million for debut storage fund

The Copenhagen firm will buy ready-to-build battery and flexibility assets, with 2degrees backing the first close.

Infrastructure

Anthropic takes over $3.4bn Caterpillar generator order for 1.7GW

Texas supplier OnePWR will help install the 1.7GW of generators at Anthropic sites, with sets expected within two years.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections