At a glance
- OpenAI called the efforts an "ambition" rather than a set policy.
- For investors underwriting data-center load, the program's non-binding, site-by-site terms mean none of it is a contracted obligation yet.
- The company said it will provide up to 1GW of flexible demand response and will work with utilities, regulators and policymakers on the program.
OpenAI launched a non-binding Grid Protectors Program to cut electricity demand from its future data center campuses when the US grid is strained, Data Center Dynamics reported Nov. 3.
OpenAI called the efforts an "ambition" rather than a set policy. "The arrangements will differ by location, and we will share additional commitments as they are finalized," the company said.
For investors underwriting data-center load, the program's non-binding, site-by-site terms mean none of it is a contracted obligation yet. The one cost-recovery structure OpenAI pointed to is its Georgia Power deal, under which it committed to pay the full cost of the infrastructure required to serve the data center.
The company said it will provide up to 1GW of flexible demand response and will work with utilities, regulators and policymakers on the program. Possible measures include helping grid operators supply power from on-site generation or storage, and using batteries and power controls to smooth demand fluctuations.
OpenAI framed the program around its own forecast that US data center capacity will exceed 100GW by 2030. In January the company pledged to "pay its own way" to power its Stargate data centers, and data center opposition has been a theme in the US midterm elections underway today.
Kim Greene, chairman, president and CEO of Georgia Power, said of the utility's framework: "Data centers are paying more so families and small businesses can pay less, and our goal with every contract we sign under this framework is to deliver value for them."
Data centers are paying more so families and small businesses can pay less, and our goal with every contract we sign under this framework is to deliver value for them.Kim Greene, chairman, president and CEO of Georgia Power
Reported by the Energy Transition desk from Data Center Dynamics. Published . Corrections