Microsoft files 422MW Floyd County campus, powered by Georgia Power

The October 20 filing values the 349-acre ATL80 build at $360 million and projects $35 million a year in local tax revenue.

At a glance

  1. The 349-acre site is at 0 Huffaker Road in Rome.
  2. Microsoft estimates the project will be valued at $360 million once built out and generate $35 million a year in local tax revenue.
  3. Georgia Power, which this publication reported in August had a 3.2GW grid slot underwritten by OpenAI, is listed as the power supplier for ATL80.

Microsoft filed a Development of Regional Impact application on October 20 for ATL80, a three-building data center campus in Floyd County, Georgia. The 349-acre site is at 0 Huffaker Road in Rome. Data Center Dynamics reported the filing, which lists 422MW of capacity to be supplied by Georgia Power.

Microsoft estimates the project will be valued at $360 million once built out and generate $35 million a year in local tax revenue. The buildings total up to 1,659,000 square feet. Microsoft expects completion by 2032 and 150 employees once operational. Microsoft bought the land in 2023, calling it "Project Firecracker" at the time.

Georgia Power, which this publication reported in August had a 3.2GW grid slot underwritten by OpenAI, is listed as the power supplier for ATL80. Under that arrangement, the customer pays full freight for the utility's build.

ATL80 follows ATL50, a two-building, 910,000 sq ft campus on 88 acres in Union City that Microsoft filed for in September, also set to launch in 2032. This publication described that filing at the time as a scheduling document. Microsoft already lists Rome, along with Fairburn, Douglasville, Palmetto, East Point and Tyrone, among its Georgia projects. Its Atlanta Fairwater site was slated to launch in November 2025.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported $45 billion contract would double Anthropic's committed capacity at Monarch to 920MW; Microsoft already holds 1.35GW there.

Infrastructure

OVHcloud wins Lille approval to pipe Roubaix data center heat into district heating network

The European Metropolis of Lille voted unanimously to connect the campus to R Énergies' 105MW thermal network, ten years after study began.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections