At a glance
- The pause suggests Spanish data center underwriting now has to price a permitting outcome alongside the power contract.
- The supply was meant to come partly from Solaria, one of Merlin's energy partners in the region.
- Merlin has reportedly prepared a contingency plan for the government's proposed royal decree taking effect and estimates an additional €863 million cost, mostly for battery energy storage, to adapt its facilities.
Merlin Properties has paused work on its Arasur 4 and 5 data centers in Álava because it has not secured a local electricity supply, Data Center Dynamics reported on Nov. 19.
The pause suggests Spanish data center underwriting now has to price a permitting outcome alongside the power contract.
The supply was meant to come partly from Solaria, one of Merlin's energy partners in the region. Administrative issues are affecting several Solaria solar projects, and the Basque Government has refused to authorize several planned solar farms, throwing the schedule into doubt.
Merlin has reportedly prepared a contingency plan for the government's proposed royal decree taking effect and estimates an additional €863 million cost, mostly for battery energy storage, to adapt its facilities. It expects to recoup about 35% of the extra cost.
Merlin already has one live 24MW building at Arasur, with a second due before the end of the year and a third next year.
CEO Ismael Clemente said the company will not proceed with the two paused buildings until it has sufficient guarantees of electricity supply. Merlin is working with Solaria to move that consumption to other areas of Spain with greater self-consumption capacity.
The €1.6 billion Navalmoral de la Mata project in Cáceres could also be affected. Clemente warned projected energy conditions could jeopardize full development, and its first building would initially operate at 2MW despite being designed for up to 100MW.
As Private Wealth Daily previously reported, the country tendered 937 MW of grid capacity in a coal phase-out area with no price, deadline or revenue guarantee. Merlin's constraint runs the other way: its supply schedule depends on solar farms a regional government has not authorized.
Merlin is also reportedly weighing moving part of its development capacity to Portugal and Madrid and adding a second project in Aragón.